Application No.5821 of 2023 C.SARAVANAN, J.

Both the parties have agreed that time may be extended by three

(3) months for pressing the Award.

2. Recording the same, the mandate of the Learned Arbitrator, to complete the arbitration proceedings, to pass an Award is extended by another three (3) months from today i.e., from 06.11.2023.

06.11.2023 rgm https://www.mhc.tn.gov.in/judis