Madras High CourtA/9376/2019delay condoned
Jai Balaji Industries Ltd v. M/S.R.K.M.Powergen Pvt Ltd
2019-12-06Honourable Dr Justice G. Jayachandran1 pages
A.No.9376 of 2019 in C.S.No.366 of 2016 Dr.G.Jayachandran, J.
This application has been filed by the applicant/defendant to condone the delay of 756 days in filing the Written Statement.
2. Regarding the delay in filing the Written Statement, reasonable and acceptable cause has been shown by the defendant that the matter was pending before NCLT. Hence, the delay is condoned and the application is ordered.
06.12.2019 rpl [2/2] http://www.judis.nic.in