← Library
Madras High CourtCONT P/3499/2024closed

Kcp Infra Ltd v. D.Karthikeyan Ias

2025-03-19Honourable Mr Justice G.K. Ilanthiraiyan4 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

Dated: 19.03.2025 Coram:

THE HONOURABLE MR.JUSTICE G.K.ILANTHIRAIYAN M/s.KCP Infra Ltd.

(Formerly known as "KCP Engineers Ltd) Reg. Office at no.4, Ground Floor, Aalayam Space, Ananda Road, Alwarpet, Chennai 600 018 Rep. by its Director K.Muthukumarasamy

...Petitioner

Vs.

1.D.Karthikeyan, I.A.S., Principal Secretary to Government, Municipal Administration and Water Supply Department, Secretariat, Fort St.George, Chennai 600 009 2.J.Kumaragurubaran, I.A.S., Commissioner, 3.Baskaran, 1/4

Superintending Engieer, Storm Water Drain Department,

...Respondents

PRAYER:

Contempt petition filed under Section 11 of the Contempt of Courts Act, 1971 to punish the respondents for the willful disobedience of the orders of this Court passed in WP.No.22782 of 2024 dated 07.08.2024. For Petitioner : Mr.S.Doraiswamy For Respondents For R1 : Mr.M.Murali, Standing Counsel For R2 & 3 : Mrs.P.T.Ramadevi, Standing Counsel

ORDER

This contempt petition has been filed to punish the respondents for the willful disobedience of the orders of this Court passed in WP.No.22782 of 2024 dated 07.08.2024, thereby the respondents had been directed to disburse the bill amount of Rs.43,26,00,000/- within a time frame. 2/4

2. The learned Standing Counsel appearing for the respondents submitted that the order passed by this Court in WP.No.22782 of 2024 dated 07.08.2024 has been complied with by the respondents.

3. Recording the above submission, this contempt petition is closed. However, if there is any grievance over the disbursement of the bill amount, the petitioner is at liberty to approach the appropriate forum to get the grievance redressed.

19.03.2025 Speaking Order/Non Speaking Order Index : Yes / No Netrual citation:Yes/No lok 3/4

G.K.ILANTHIRAIYAN, J.

lok To 1.D.Karthikeyan, I.A.S., Principal Secretary to Government, Municipal Administration and Water Supply Department, Secretariat, Fort St.George, Chennai 600 009 2.J.Kumaragurubaran, I.A.S., Commissioner, 3.Baskaran, Superintending Engieer, Storm Water Drain Department, 4.The Public Prosecutor, High Court of Madras 19.03.2025 4/4