IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 21.12.2020 CORAM :

The HON'BLE MR.JUSTICE M.DURAISWAMY W.P.No.25992 of 2017 A. Venkadachalam ... Petitioner v.

1.The District Collector, Collectorate, Salem District.

2. The Joint Engineer, Power grid NM Transmission Ltd., 400 KV Substation Konakapadi Post, KR Thoppur, Salem, Tamil Nadu - 636 502.

... Respondents Writ Petition filed under Article 226 of the Constitution of India for issuing a Writ of Mandamus directing the respondents herein to consider the petitioner's representation dated 20.06.2016 and enhance the petitioner compensation.

For Petitioner : Mr. A. Rajkumar, For Respondents : Ms. A. Mathumathi, Special Govt. Pleader - R1 No Appearance - R2

O R D E R

The petitioner has filed the above Writ Petition to issue a Writ of Mandamus directing the respondents to consider the petitioner's representation dated 20.06.2016 and enhance the compensation.

2. Mr. A. Rajkumar, learned counsel appearing for the petitioner submitted that though the petitioner has e given his representation as early as on 20.06.2016, the 1st respondent has not passed any order sofar.

3. Ms.A.Mathumathi, learned Special Government Pleader appearing for the 1st respondent submitted that in the event of the petitioner giving fresh representation to the Special Tahsildar (Land Acquisition), the same shall be considered in https://hcservices.ecourts.gov.in/hcservices/ Page numbers

accordance with law.

4. The learned counsel appearing for the petitioner submitted that three weeks time may be granted to the petitioner to give fresh representation to the Special Tahsildar (Land Acquisition).

5. Having regard to the submissions made by the learned counsel on either side, taking into consideration the limited prayer sought for by the learned counsel for the petitioner, I grant three weeks time to the petitioner to submit a fresh representation to the Special Tahsildar (Land Acquisition), seeking for enhancement of the compensation and on receipt of the same, the Special Tahsildar (Land Acquisition) shall pass orders, on merits and in accordance with law, after giving notice to the petitioner, within a period of six weeks from the date of submission of the representation.

With these observations, the Writ Petition is disposed of. No costs.

Sd/- Assistant Registrar //True Copy// Sub Assistant Registrar Rj To 1.The District Collector, Collectorate, Salem District.

2. The Joint Engineer, Power grid NM Transmission Ltd., 400 KV Substation Konakapadi Post, KR Thoppur, Salem, Tamil Nadu - 636 502.

+1cc to the Government Pleader SR.42495 W.P.No.25992 of 2017 AJS(CO) CB(18/01/2021) https://hcservices.ecourts.gov.in/hcservices/ Page numbers