C.M.P.No.22541 of 2025 in A.S.SR.No.141257 of 2025 P.B.BALAJI, J.
The orders passed by this Court on 20.11.2025 and 11.12.2025 has been complied with. The learned counsel for the respondents also affirms the same.
2. In light of the above, the order dated 20.11.2025 condoning the delay of 650 days in filing the appeal is hereby confirmed.
3. Hence, complied with.
22.01.2026 Jeni Note: Registry is directed to number and list the appeal for admission before the Joint Registrar, Appellate Side, if it is otherwise in order.