IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 21.02.2024

CORAM

THE HONOURABLE MR.JUSTICE S.M.SUBRAMANIAM and THE HONOURABLE MR.JUSTICE K.RAJASEKAR T.Jayamala ... Petitioner Vs.

1. The Commissioner, Director of Town and Country Planning, Chengalvarayan Building, No.807, 4th Floor, Anna Salai, Chennai - 600 002.

2. The Deputy Director, Director of Town and Country Planning, Salem Region, Soornamangalam, Salem.

3. The Commissioner, Attur Municipality, Municipality Office, Attur, Salem - 636 102.

4. The Executive Engineer, Operation and Maintenance, TANGEDCO, Attur Town, Salem District - 636 102.

5. Mani

6. Dhanalakshmi ... Respondents Prayer: Writ Petition is filed under Article 226 of the Constitution of India, to issue a Writ of directing the respondents 1, 2 and 3 to take appropriate and necessary steps to demolish the unauthorized construction made by the 5th and 6th respondents at Door No. 1019, Block No. 28, South Udayarpalayam, Attur, Salem District by considering the petitioner's representation dated 12.02.2019, 12.04.2019, 06.05.2019 and 07.05.2019. For Petitioner : Mrs.R.S.Maitreya For R1 & R2 : Mr.A.Selvendran, Special Government Pleader For R3 : MR.P.Srinivas, Standing Counsel For R4 & R6 : No appearance For R5 : Mr.N.C.Ashok Kumar

O R D E R

(Order of the Court was made by S.M.SUBRAMANIAM, J.) Since the application submitted by the writ petitioner seeking regularization was rejected and as of now, the scheme for regularization is not in force, the unauthorized constructions are to be removed by following the procedures. Thus, the respondents are directed to initiate all appropriate actions to remove the unauthorized constructions by following the

procedures as contemplated under the Statutes and Rules in force. The said exercise is directed to be completed within a period of two weeks from the date of receipt of a copy of this order.

2. Accordingly, the Writ Petition stands disposed of. No costs. (S.M.S.,J.) (K.R.S.,J.) 21.02.2024 skr Index : Yes To

1. The Commissioner, Director of Town and Country Planning, Chengalvarayan Building, No.807, 4th Floor, Anna Salai, Chennai - 600 002.

2. The Deputy Director, Director of Town and Country Planning, Salem Region, Soornamangalam, Salem.

3. The Commissioner, Attur Municipality, Municipality Office, Attur, Salem - 636 102.

4. The Executive Engineer,

Operation and Maintenance, TANGEDCO, Attur Town, Salem District - 636 102.

S.M.SUBRAMANIAM, J.

and K.RAJASEKAR, J.

skr 21.02.2024