United Alliance Health Care Pvt Ltd And 2 Others v. Dr.N.Rajamaheswari And Another
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 23.02.2026
CORAM
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH Application No.4564 of 2025
1. United Alliance Health Care P Ltd Represented by its Director Dr.T.Palaniappan Old No.28, New No.22, Arcot Street, T.Nagar, Chennai 600 017
2. Dr.T.Palaniappan Old No.28, New No.22, Arcot Street, T.Nagar, Chennai 600 017
3. Mr.Narendra Srisrimul 4B Heritage Apartments, 4th Cross, Ormes Road, Kilpauk, Chennai 600 010 .... Applicants/Judgement Debtor 1 to 3 Vs.
1. Dr.N.Rajamaheshwari No.18, C.P.Ramasamy Road, Alwarpet, Near Canara Bank, Abiramapuram, Chennai 600 018 ... 1st Respondent/Applicant /Decree holder
2. Innovative Health Care LLP Represented by its Partner, Dr.T.Palaniappan, Old No.28, New No.22, Arcot Street, T.Nagar, Chennai 600 017 ..2nd respondent/4th respondent / 4th Judgement Debtor PRAYER 1/4
Application filed under Order XIV Rule 10 (xii) of OS Rules r/w Order I, Rule 10(2) of CPC, praying to stike off the applicants herein / Respondents 1 to 3 in the above EA No.2267 of 2025. For Applicant : Mr.B.Deepak Narayanan For Respondents : Mr.V.Ravi for R1 Mr.M.Devesh Kumar for r2 *****
ORDER
This application has been filed by the respondents 1 to 3 / Judgement debtors 1 to 3 to strike off their names in the Application No.2267 of 2025 in EP (Com.Div) SD No.42694 of 2025. 2.
Heard Mr.B.Deepak Narayanan, learned counsel for the applicant and Mr.V.Ravi, learned counsel for 1st respondent and Mr.M.Devesh Kumar, learned counsel for 2nd respondent. 3.
As per the award dated 01.03.2023, paragraph 195(c) reads as follows :- "195(c) All the Respondents shall jointly and severally pay the claimant a sum of Rs.4,22,302.05/- as costs." 2/4
4.
It is clear from the above that insofar as the respondents 1 to 3 / Judgement Debtors 1 to 3 are concerned, their liability is joint and several insofar as the payment of cost.
5.
A memo has been filed and the relevant portions are extracted hereunder:- 4.
It is submitted that the costs portion as provided under Relief (c), together with interest comes to a total value of Rs.5,17,788.59/-. The calculation of the same is provided below: Cost awarded :
Rs.4,22,302.05/- Interest @ 9% (From 01.03.2023 to 03.09.2025) (being 2% higher than the current rate of interest u/s.31(7)(b) of Arbitration and Conciliation Act, 1996):
Rs. 95,486.54/- --------------------- Rs. 5,17,788.59/- ---------------------
5. It is submitted that without prejudice to the Applicant's rights and Privileges including but not limited to legal or equitable rights or right to challenge the cost portion of the Award has been complied in pursuant to the payment of Rs.5,18,000/- by way of demand draft, bearing 000762 dated 01.09.2025 to the Decree holder. The copy of the covering letter (with postal receipt / tracking) along with copy of demand draft is annexed herewith for reference.
3/4
N.ANAND VENKATESH.,J rka 6.
In view of the above, it is seen that the relief granted as against respondents 1 to 3 has been complied with and therefore, the respondents 1 to 3 /Judgement Debtors 1 to 3 need not continue to be shown as parties in this application.
7.
In the result, this application is ordered as prayed for. 23.02.2026 rka Application No.4564 of 2025 4/4