← Library
Madras High CourtWMP/37674/2024closed

The Project Director National Highways Authority Of India v. R.Palanivel

2025-03-10Honourable Mr Justice N. Anand Venkatesh3 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 10.03.2025

CORAM

THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH in W.P.No.2171 of 2019 The Project Director, National Highways Authority of India, PIU, Salem, Door No.212-3/D3-1, Sri Nagar Colony, Narasothipatti, Salem - 636 004.

.. Petitioner Vs.

1.R.Palanivel 2.The Competent Authority & District Revenue Officer, Collectorate Building, Namakkal District.

3.The Special Tahsildar, (Land Acquisition), National Highways (Unit-I), Namakkal.

.. Respondents Prayer: Petition filed under Article 226 of the Constitution of India praying to pass an order to implead the petitioner as 3rd respondent in the instant in W.P.No.2171 of 2019.

1/3

For petitioner :

Mr.SU.Srinivasan For R1 :

Mr.S.Senthil For RR 2 & 3 :

Mr.P.Sathish Additional Government Pleader

O R D E R

This petition has been filed to implead the petitioner herein as 3rd respondent in W.P.No.2171 of 2019.

2.Heard the learned counsel for the petitioner, learned counsel for the 1st respondent and the learned Additional Government Pleader for the respondents 2 & 3.

3.Being satisfied with the reasons stated in the affidavit filed in support of this writ petition, this petition is ordered as prayed for. 10.03.2025 (1/2) krk NOTE: Registry is directed to carry out necessary amendment in the cause title in W.P.No.2171 of 2019 2/3

N.ANAND VENKATESH, J.

krk 10.03.2025 (1/2) 3/3