M/S.New India Assurance Company Ltd v. Manga
CMP NO. 28883 of 2024
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 17-12-2024
CORAM
THE HONOURABLE MRS JUSTICE J. NISHA BANU AND THE HONOURABLE MR.JUSTICE R.SAKTHIVEL CMP NO. 28883 of 2024 in CMA.SR.No.157063 of 2024 M/s.New India Assurance Company Ltd The Branch Manager, 14/7 Kg Swamy Complex Bagalur Road Hosur Taluk Dharmapuri Tamil Nadu 636701 Appellant(s) Vs Manga W/o. Ravi Eb Office Quarters, Kozhimekkanur Village, Pappireddipatti Post, Dharmapuri District 636 905 Now At Mookkanur Village And Post, Dharmapuri Taluk And Dist, 635 202 and 5 Others Respondent(s) For Appellant(s):
Mr.C.Johnson
ORDER
This miscellaneous petition has been filed to condone the delay of 95 days in paying the deficit court fee.
2. Heard the learned counsel for the petitioner. 3.Considering the submission made and on being satisfied with reasons stated in the affidavit, this Court is of the view that the delay may https://www.mhc.tn.gov.in/judis
-2J.NISHA BANU, J.
and R.SAKTHIVEL,J.
vsi be condoned, however, on payment of cost. Accordingly, the delay is condoned on payment of cost of Rs.1,000/- (Rupees One Thousand only) by the petitioner to the Tamilnadu Legal Aid Services Authority, Chennai, on or before 06.01.2025. If the cost is not paid on or before 06.01.2025, this C.M.P. stands dismissed without any reference to this Court. (J.N.B.,J.) (R.S.V.,J.) 17-12-2024 vsi CMP No. 28883 of 2024 in CMA.SR.No.157063 of 2024 https://www.mhc.tn.gov.in/judis