← Library
Madras High CourtWP/35496/2019disposed of

N.Sudha v. Government Of Tamil Nadu

2023-09-25Honourable Mrs Justice J. Nisha Banu,Honourable Mrs Justice N. Mala1 pages

W.P.No.35496 of 2019 J.NISHA BANU, J.

and N.MALA,J.

Today the matter is listed under the caption 'for reporting compliance'.

2. The learned counsel appearing for the petitioner submitted that as per the order of this Court, the official respondents has de-sealed the petitioner's premises only on 18.12.2023 and now demolition work has also been started by the petitioner and hence prayed for further extension of time to comply with the order dated 25.09.2023.

3. Since, the petitioner's premises was de-sealed only on 18.12.2023, a further period of twelve weeks is granted from today.

4. Post the matter on 12.03.2024 'for reporting compliance'.

(J.N.B,J.) (N.M.,J.) 22.12.2023 sk https://www.mhc.tn.gov.in/judis