← Library
Madras High CourtCONT P/3709/2025closed

M.J.Sankar v. J.Kumaragurubaran And 3 Others

2026-01-30Honourable Mr Justice P. Velmurugan,Honourable Mr.Justice M.Jothiraman5 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 30-01-2026

CORAM

THE HONOURABLE MR JUSTICE P.VELMURUGAN AND THE HONOURABLE MR.JUSTICE M.JOTHIRAMAN MJ.Sankar No.3/1, Thirumurthy Street T.Nagar, Chennai 600 017 Petitioner Vs

1. J.Kumaragurubaran Chief Commissioner Greater Chennai Corporation Rippon Building, EVR Periyar Salai Chennai 600 003

2. C.Chokkalingam The Executive Engineer Greater Chennai Corporation No.61, Basin Bridge Road Chidambaram Nagar, Mint Chennai 600 021

3. Tmt.Kakarla Usha Additional Chief Secretary to Government Housing and Urban Development Department Secretariat, Chennai 600 009

4. Body Story Studios rep.by its Authorised Representative, R.Ronak Gugaliya No.72/2, Jermiah Road Vepery, Chennai 600 007 Contemnors

Contempt Petition filed under Section 11 of the Contempt of Courts Act, 1971 praying to punish the respondents 1 to 3 for wilful disobedience of the order of this Court dated 03.06.2025 passed in W.P.No.18065 of 2025. For Petitioner:

Mr.MJ.Sankar Party-in-Person For Contemnors:

Mr.E.C.Ramesh Standing Counsel for R1 & R2 Mr.M.Murali Government Advocate for R3

ORDER

(Order of the Court was made by P.Velmurugan J.) Alleging wilful disobedience of the order of this Court dated 03.06.2025 on the part of the respondents 1 to 3, the present contempt petition has been filed before this Court.

2. The petitioner, appearing in person, would submit that the order of this Court has not been complied with in letter and spirit and though the official respondents found that the fourth respondent had put up the illegal structure unauthorisedly and there have been deviations, still they have not taken any action to remove the illegal construction/deviations, as the case may be.

3. The learned Standing Counsel appearing on behalf of the respondents 1 & 2 would submit that based on the order passed by this Court dated 03.06.2025, the official respondents conducted enquiry and issued the Form-V

notice dated 25.08.2025 directing the fourth respondent to discontinue the subject building and also subsequently locked and sealed the subject building on 04.09.2025. Challenging the said order, the fourth respondent preferred a revision under Section 80-A of the Tamil Nadu Town and Country Planning Act, 1971 before the Government, which was disposed of by the Government on 11.12.2025 after giving opportunity to all the parties concerned. Now challenging the said order, Writ Petition No.357 of 2026 filed by one Mr.S.Ramesh Kumar in respect of the subject building is pending before the writ Court. Therefore, leaving it open to the petitioner to workout his remedy in the pending Writ Petition No.357 of 2026, this contempt petition stands closed. (P.VELMURUGAN J.) (M.JOTHIRAMAN J.) 30-01-2026 ss

To

1. The Chief Commissioner Greater Chennai Corporation Rippon Building, EVR Periyar Salai Chennai 600 003

2. The Executive Engineer Greater Chennai Corporation No.61, Basin Bridge Road Chidambaram Nagar, Mint Chennai 600 021

3. The Additional Chief Secretary to Government Housing and Urban Development Department Secretariat, Chennai 600 009

P.VELMURUGAN J.

AND M.JOTHIRAMAN J.

ss CONT P No. 3709 of 30-01-2026