← Library
Madras High CourtCONT P/3920/2024closed

M/S. Kcp Infra Ltd., v. Thiru. D. Karthikeyan, I.A.S., And 2 Others

2025-09-10Honourable Mr Justice G.K. Ilanthiraiyan4 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 10.09.2025

CORAM

THE HONOURABLE Mr. JUSTICE G.K.ILANTHIRAIYAN M/s.KCP Infra Ltd., (Formerly known as "KCP Engineers Ltd.) No.4, Ground Floor, Aalayam Space, Ananda Road, Alwarpet, Chennai - 600 018, Rep by its Director, K.Muthukumarasamy ... Petitioner in all Cont.Ps.

Vs.

1. D.Karthikeyan, I.A.S., Principal Secretary to Government, Municipal Administration and Water Supply Department, Secretariat, Chennai - 600 009.

2. J.Kumaragurubaran, Commissioner, Greater Chennai Corporation, Ripon Building, Chennai - 600 003.

3. Baskaran, Superintending Engineer, Storm Water Drain Dapartment, Greater Chennai Corporation, Ripon Building, Chennai - 600 003.

... Respondents in all Cont.Ps.

Common Prayer:- Contempt petitions have been filed under Section 11 of the Contempt of Courts Act, 1971, praying to punish the respondents for the willful disobedience of the orders of this Court passed in W.P.Nos.24734, 24736 & 24737 of 2024 respectively, dated 23.08.2024 under the provisions of Contempt of Courts Act.

In all Cont.Ps.

For Petitioner : Mr.S.Doraisamy For Respondents For R1 : Mr.M.S.Premkumar Government Advocate For R2 & R3 : Mr.E.C.Ramesh Standing Counsel COMMON ORDER These Contempt Petitions have been filed to punish the respondents for non compliance of the common order dated 23.08.2024, passed by this Court in W.P.Nos.24734, 24736 & 24737 of 2024 respectively, thereby directing the respondents to allocate the work site to the petitioner in order to complete the remaining work as per the word orders dated 05.02.2021, 11.02.2021 & 20.02.2021, within a period of four weeks.

2.

The learned Standing Counsel appearing for the respondents 2 & 3 submitted that as directed by this Court, the respondents allotted work site in three packages to the petitioner. He also produced an affidavit filed by the second respondent along with the details of work allotted to the petitioner before this Court.

3.

Recording the said submission, all the Contempt Petitions stand closed.

10.09.2025 Index : Yes/No : Yes/No Speaking/Non Speaking order rts To

1. The Principal Secretary to Government, Municipal Administration and Water Supply Department, Secretariat, Chennai - 600 009.

G.K.ILANTHIRAIYAN, J.

rts

2. The Commissioner, Greater Chennai Corporation, Ripon Building, Chennai - 600 003.

3. The Superintending Engineer, Storm Water Drain Dapartment, Greater Chennai Corporation, Ripon Building, Chennai - 600 003.

10.09.2025