R.Balaji Premraj, v. Dr.J.Radhakrishnan, I.A.S., And 2 Others
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 31.01.2025
CORAM
THE HONOURABLE MR.JUSTICE R.SUBRAMANIAN and THE HONOURABLE MR.JUSTICE V.LAKSHMINARAYANAN R.Balaji Premraj S/o.A.Ramamoorthy .. Petitioner Vs.
1. Dr.J.Radhakrishnan Commissioner Greater Chennai Corporation Ripon Buildings Chennai-600 003.
2. Thiru.P.V.Srinivasan Zonal Officer, Zone XII Greater Chennai Corporation No.1, New Street, Alandur Now in SIDCO Industrial Estate Nagi Reddy Street Guindy, Chennai-600 032.
3. Thiru.S.Naren S/o.Santhanam .. Respondents Contempt petition filed under Section 11 of the Contempt of Courts Act, 1971 praying to punish the respondents for wilful disobeyal of the orders of the Hon'ble High Court, Madras made in W.P.No.24768 of 2022 dated 02.03.2023.
1/3
For Petitioner :
Mr.T.Ranganathan For Respondents :
Mr.D.B.R.Prabhu Standing Counsel for R1 & R2 *****
O R D E R
(Order of the Court was made by R.SUBRAMANIAN, J.) The learned counsel for Corporation would submit that the premises has been locked and sealed on 18.09.2024 as per directions of Hon'ble Division Bench in its order dated 28.06.2023 since the undertaking given to the Government was not complied with.
2. The learned counsel for Corporation would submit that further action to remove unauthorized construction will be taken in due course.
3. Recording the above submission, this Contempt Petition is closed. If the unauthorized construction is not removed within a period of twelve (12) weeks from today, the petitioner will be at liberty to seek for reopening of the contempt petition.
(R.S.M,J.) (V.L.N.,J.) 31.01.2025 Index:No Speaking order mk 2/3
R.SUBRAMANIAN.J., and V.LAKSHMINARAYANAN, J., mk 31.01.2025 3/3