← Library
Madras High CourtCONT P/3868/2025closed

K.Nagarajan, v. Mr. J.Radhakrishnan And 3 Others

2026-01-27Honourable Dr.Justice R.N.Manjula4 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 27-01-2026

CORAM

THE HON'BLE DR.JUSTICE R.N.MANJULA K.Nagarajan, S/o. Krishnan, No.200/25, IX Cross Street, Kamaraj Nagar, Sipcot Post, Hosur Taluk, Krishnagir Dsitrict, ..Petitioner(s) Vs

1. Mr. J.Radhakrishnan Chairman Cum Managing Director of TANGEDCO, No. 144, Anna Salai, Chennai - 2.

2. Mr. Ramalingam, Chief Engineer, Tamil Nadu Generation and Distribution Corporation Ltd., Gandhi Nagar, Katpadi, Vellore District

3. Tmt. Komagal, Tamil Nadu Generation and Distribution Corporation Ltd., Dharmapuri Electricity Distribution Circle, Dharmapuri - 5.

4. Mrs. Kavitha (Incharge), Tamil Nadu Generation and Distribution Corporation Ltd., Krishnagiri Electricity Distribution Circle, ..Contemnor(s) PRAYER - This Contempt Petition is filed under Section 11 of the Contempt of Courts Act to punish the respondents for non-compliance of the order passed in W.P.No. 2584 of 2019 dated 03.04.2025.

For Petitioner(s):

Mr.S.N. Ravichandran, For Contemnor(s):

Mr. C.Manoharan, Standing Counsel

O R D E R

This Contempt Petition is filed to punish the respondents for noncompliance of the order passed in W.P.No. 2584 of 2019 dated 03.04.2025. 2.A proceedings has been issued by the 3rd respondent by giving promotion to the petitioner from the date on which he is eligible to get promotion and as per the orders of this Court and also by giving notional impact.

3.However, the learned counsel appearing for the petitioner submitted that despite the proceedings has stated that the notional impact is given in view of the retrospective promotion, the same has not been implemented in realistic terms.

4.However, on perusal of the order, it is seen that in the bottom of the proceedings, an instruction has been given to the Executive Engineer to re-fix the salary by giving notional impact as per the order of the Court and disburse the arrears to the petitioner. A comprehensive order has been passed inclusive of the possible mandatory benefit that might flow to the petitioner. 5.Hence, compliance of the order is recorded and further action is dropped. Accordingly, this Contempt Petition is closed. 27-01-2026 Index: Yes/No Speaking/Non-speaking order GSA

DR.R.N.MANJULA, J.

GSA To

1. Mr. J.Radhakrishnan Chairman Cum Managing Director of TANGEDCO, No. 144, Anna Salai, Chennai - 2.

2. Mr. Ramalingam, Chief Engineer, Tamil Nadu Generation and Distribution Corporation Ltd., Gandhi Nagar, Katpadi, Vellore District.

3. Tmt. Komagal, Tamil Nadu Generation and Distribution Corporation Ltd., Dharmapuri Electricity Distribution Circle, Dharmapuri - 5