M/S.Era Infra Engineering Ltd (Eiel) v. Bharat Heavy Electricals Limited
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 19-12-2025
CORAM
THE HONOURABLE Mr. JUSTICE N. ANAND VENKATESH A.No. 6330 of 2025 M/s.Era Infra Engineering Ltd (EIEL) Through its Authorized Representative Mr.Niladri Chatterji DGM Projects C-56/41, Sector 62, Noida Uttar Pradesh 201301 Applicant Vs Bharat Heavy Electricals Limited Power Sector Southern Region 690, Anna Salai, Nandanam Chennai - 600 035 Respondent PRAYER To pass an order of granting a period of further 6 months Extension of time for passing of Arbitral award in the above matter to the Judge's summons. For Applicant:
Mr.V.Sivabalan For Respondent:
Mrs.Mithreyi Kasthurirangan
ORDER
This application has been filed under Section 29A of the Arbitration and Conciliation Act, 1996, seeking for extension of mandate of the Arbitral Tribunal. https://www.mhc.tn.gov.in/judis
N. ANAND VENKATESH, J.
gya
2. Heard both sides.
3. It is brought to the notice of this Court that the arbitration proceedings is at the stage of passing final orders. Hence, considering the stage of the proceedings and after hearing both sides, the period is extended by three months from the date of receipt of a copy of this order.
This application is disposed of in the above terms. 19.12.2025 gya A.No.6330 of 2025 https://www.mhc.tn.gov.in/judis