M/S.Arunachalam Projects And Infrastructure Pvt. Ltd., v. E. Mohan
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 21.11.2025
CORAM:
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH Application No.5798 of 2025 M/s.Arunachalam Projects & Infrastructure Pvt. Ltd., Represented by V.Parthasarathy Arunachala Building 2nd Floor, No.107/76 Avvai Shanmugam Salai (Lloyds Road) Royapettah, Chennai Tamil Nadu - 600 014.
... Applicant -VsMr.E.Mohan Rep. of M/s.Sri Krishna Lorry Service (Also known as M/s.SKLS Lorry Service) Survey No.93/1c/2b GNT Road, Redhills Chennai-600 052.
... Respondent Prayer:
Application filed under Order XIV Rule 8 of O.S. Rules read with Section 29A(5) of the Arbitration and Conciliation Act, 1996, praying to extend the time for completion of arbitration proceedings by a period of four
(4) months.
For Applicant :
Mr.Prithvi Raj M/s.AK Mylsamy & Associates LLP For Respondent :
Mr.Rahul Balaji 1/3
O R D E R
This application has been filed under Section 29A of the Arbitration and Conciliation Act, 1996 (Act No.26 of 1996) seeking for extension of time for completion of pleadings and for passing final award by the Arbitral Tribunal.
2. Heard the learned counsel for the applicant and the learned counsel for the respondent.
3. It is brought to the notice of this Court that the arbitral proceedings is now at the stage of final arguments.
4. Taking into consideration the above submission, the time is extended for a period of three months from the date of receipt of a copy of this order, for passing the final award.
This Application is disposed of in the above terms. 21.11.2025 mk Index: Yes/No Speaking Order/Non-Speaking Order 2/3
N.ANAND VENKATESH, J.
mk Application No.5798 of 2025 21.11.2025 3/3