Rpn Engineers Chennai Private Limited v. The General Manager
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 11-12-2025
CORAM
THE HONOURABLE MR JUSTICE N. ANAND VENKATESH A No. 5939 of 2025 in Arb.OP(Com.Div)D.No.181867 of 2025 RPN Engineers Chennai Private Limited M-60, 9th Street, Anna Nagar East, Chennai - 600 002.
Applicant(s) Vs
1. The General Manager Southern Railway, Park Town, Chennai - 600 003.
2.The Chief Engineer / West, Construction, Southern Railway, Egmore, Chennai - 600 008.
Respondent(s) PRAYER To condone the delay of 9 days in filing Arb.O.P. Diary No.181869 of
2025.
For Applicant(s):
J.Srinivasa Mohan
ORDER
This petition has been filed to condone the delay of 9 days in filing the Arbitration Original Petition under Section 34 of the Arbitration and Conciliation Act, 1996.
2.Proof of service has been filed and the name of the respondent has been printed in the cause list. There is no appearance either in person or through counsel.
3.Heard.
4.Having satisfied with the reasons assigned in the affidavit filed in
support of this petition, the petition is allowed and the delay of 9 days is condoned. Registry is directed to number the petition, if the papers are otherwise in order.
11-12-2025 Index:Yes/No Speaking/Non-speaking order Internet:Yes kp To 1.The General Manager Southern Railway, Park Town, Chennai - 600 003.
2.The Chief Engineer / West, Construction, Southern Railway, Egmore, Chennai - 600 008.
N.ANAND VENKATESH J.
kp A No. 5939 of 2025 in Arb.OP(Com.Div)D.No.
181867 of 2025
11-12-2025