← Library
Madras High CourtWP/45037/2025disposed of with direction

A.R.Ravichandran v. The Inspector

2025-11-19Honourable Mr Justice M.Dhandapani6 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 19-11-2025

CORAM

THE HONOURABLE MR JUSTICE M.DHANDAPANI A.R.Ravichandran Petitioner(s) Vs

1. The Inspector General of Registration, Office of the Inspector General Of Registration, Santhome High Road, Chennai 28.

2.The District Registrar (North) Office of the Registrar of Societies, First Line Beach, Chennai 01.

3.The President, Emaar Esplanade Apartment Owners Welfare Association, (Regn No. 214/ 2010 ) No. 75 Vaithiyanathan Street, Tondiarpet, Chennai 81.

Respondent(s) PRAYER;This writ petition is filed under Article 226 of Constitution of India, to issue a Writ of Mandamus, directing the 2nd respondent to pass orders initiated under Letter No. 14312/ E1/ 2023 dated 23.01.2024 on the petitioners representation dated 21.12.2023 within a time frame fixed by this Honble court.

For Petitioner(s):

Mr.S.Girissh For Respondent:

Mr.M.S.Arasakumar, GA RR1 & 2

ORDER

This petition has been filed seeking a direction to the 2nd respondent to pass orders initiated under Letter No. 14312/ E1/ 2023 dated 23.01.2024 on the petitioners representation dated 21.12.2023.

2. It is the case of the petitioner that he is a member of the Association who has brought to light serious financial irregularities including the misappropriation of Rs.16,20,606/-, falsification of accounts, manipulation of records and violation of statutory procedures. Based on the complaint lodged by the petitioner, the second respondent initiated an enquiry and accordingly, conducted a hearing on 11.11.2025 during which the petitioner produced all the relevant documents including accounts, minutes and evidences for the

misappropriation. However, the respondents have not taken any action to the members who have involved in the misappropriation. Therefore, the petitioner made a representation to the respondents on 21.12.2023 and the same was acknowledged by the respondent on 23.01.2024. However, the respondents have not conclude the proceedings. Hence, the present writ petition.

3. The learned counsel for the petitioner submitted that this Court may direct the respondents to conclude the proceedings dated 23.01.2024 within the stipulated time as fixed by this Court.

4. The learned Government Advocate appearing for the respondents submitted that the proceedings will be concluded and appropriate action will be taken within the stipulated time as fixed by this Court.

5. Heard the learned counsel for both side and perused the materials available on record.

6. Considering the facts and circumstances of the case and in view of the

limited request sought for by the petitioner, this court directs the second respondent to conclude the proceedings dated 23.01.2024 and pass orders on the petitioner's complaint within a period of four weeks from the date of receipt of a copy of this order, after providing opportunity to the petitioner as well as the necessary members of the third respondent.

7. With the above directions, the writ petition is disposed of. No costs. 19-11-2025 rli Index:Yes/No Speaking/Non-speaking order Internet:Yes

M.DHANDAPANI J.

rli To 1.The Inspector General Of Registration, Office Of The Inspector General of Registration, Santhome High Road, Chennai 28 2.The District Registrar (North) Office Of The Registrar of Societies, First Line Beach, Chennai 01 19-11-2025