N.Srinivasan v. M/S.Mangai Engineers
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 19-12-2025
CORAM
THE HONOURABLE Mr. JUSTICE N. ANAND VENKATESH A.No.6280 of 2025 N.Srinivasan Applicant(s) Vs 1.M/s.Mangai Engineers Rep by its Proprietrix Mrs. R.Mangayarkarasi W/o.M.Ravi, Shop No.74, 2nd Floor, J.J.Complex Thirumangalam, Anna Nagar, Chennai - 600 040 2.R.Mangayarkarasi Proprietrix of M/s.Mangai Engineers, No.2/12A, 3rd Floor Galaxy Apartment, Nolambur, Mogappair West Chennai - 600 037 3.M.Ravi CEO of M/s.Mangai Engineers, No.14, Manniyakarar Street Veera Keralam, Coimbatore, Tamilnadu - 641 007 Respondent(s) PRAYER To extend the time for completion of the Arbitration proceeding for a period of 6 months from 13.09.2025 and thus render justice. For Applicant(s):
Mr.M.Gopalakrishnan For Respondent(s):
Mr.P.Mohanraj
ORDER
This application has been filed under Section 29A of the Arbitration and Conciliation Act, 1996, seeking for extension of mandate of the Arbitral Tribunal.
https://www.mhc.tn.gov.in/judis
N. ANAND VENKATESH, J.
gya
2. Heard both sides.
3. It is brought to the notice of this Court that the arbitration proceedings is at the stage of final arguments. Hence, considering the stage of the proceedings and after hearing both sides, the period is extended by three months from the date of receipt of a copy of this order. This application is disposed of in the above terms. 19.12.2025 gya A.No.6280 of 2025 https://www.mhc.tn.gov.in/judis