A.No. 6055 of 2025 in C.S.(COMM DIV).DR.No. 195687 of 2025 MASTER 09.12.2025 Order This is an application to condone the delay of 12 days in representing the suit. The reason stated for the delay is that due to the technical issues in the e-filing portal delay occurrred in representation.
The delay is in refiling only and not in filing. This court has come across many number of cases in which leniency was shown in condoning the delay in refiling. Following the same analogy this court is inclined to condone the delay and this application is allowed. No cost.