Tata Capital Ltd v. Priya Chandrasekar
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 12.01.2026
CORAM
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH Arbitration Application No.1637 of 2025 Tata Capital Limited, by its Associate Legal Remedial, R. Kamalakannan, having its office at 1st Floor, Centennial Square, 6A-Dr.Ambedkar Salai, Kodambakkam, Chennai 600 024 .... Applicant Vs.
Priya Chandra Sekar 4 273 Pushpagiri Main Road, Hayath Nagar, Land MarkRation Shop, , Padapapai, Kancheepuram 601 301 Tamil Nadu ..... Respondent Arbitration Application under Order XIV Rule 8 of Original Side Rules r/w Section 9 (ii) (d) & (e) of the Arbitration and Conciliation Act, 1996, praying to appoint a receiver namely Mr.Abish DJ, employed as Legal Manager in the Applicant company having his office at First Floor, Centennial Square, Dr. Ambedkar Salai, Kodambakkam, Chennai, Tamil Nadu 600 024 as Receiver to seize and deliver the asset MARUTHI SWIFT ZXI + bearing Engine No.K12MP1121253 Chassis No.MBHCZC63SKK501315, Registration No.TN11AR6026 situated at 4 273, Pushpagiri Main Road, Hayath Nagar, Padapapai, Land mark-Ration Shop, Kanchipuram 601 301, Tamil Nadu, or wherever it is found more fully described in the judges summons with police aid or break open the premises from wherever found and handover the same to the applicant.
For Applicant : Mr. N.K. Vanan __________Page 1 of 4
*****
ORDER
This application has been filed under Section 9 of the Arbitration and Conciliation Act, 1996 [for brevity 'the Act'] for appointment of a receiver to seize and deliver the Construction Equipment to the applicant, if required, with police aid.
2. The applicant extended financial facilities to the respondents. Since the respondents committed default, a recall notice dated 17.10.2025 was issued and in spite of receipt of the same, there was no response from respondent. It is under these circumstances, the present petition came to be filed before this Court.
3. When the application came up for hearing on 03.12.2025 this Court issued notice to respondent.
4. Private notice has been served on the respondent and affidavit of service has also been filed. The names of respondent has also been printed in the cause list. However, the respondent is neither present nor represented through counsel. Hence, the apprehension raised on the side of the applicant that the respondent is trying to secret the Construction Equipment is prima facie established.
__________Page 2 of 4
5. In view of the above, Mr.Abish DJ, Legal Manager is appointed as the Court receiver and the Court receiver is permitted to seize the Construction Equipment from the respondents or wherever it is found and by breaking open the premises, if required with police assistance. This application stands disposed of in the above terms. 12.01.2026 msr N.ANAND VENKATESH, J.
msr __________Page 3 of 4
Arbitration Application No.1637 of 2025 12.01.2026 __________Page 4 of 4