G.Sampanki v. Dr.J.Radhakrishnan, Ias And 2 Others
2026:MHC:340
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 22-01-2026
CORAM
THE HONOURABLE Mr.JUSTICE C.KUMARAPPAN
1. G.Sampanki Junior Engineer Grade-I 110 KVSS-Vettavalam Section, Tiruvannamalai East Division Tiruvannamalai Distribution Circle, Tiruvannamalai District.
Petitioner(s) Vs
1. Dr.J.Radhakrishnan, IAS., The Chairman and Managing Director Tamil Nadu Electricity Board/TANGEDCO, NPKRR Maligai, No.144 Anna Salai Chennai-600 002.
2.Mrs.M.Ambiga The Chief Engineer (Personnel) Tamil Nadu Electricity Board/TANGEDCO NPKRR Maligai No.144, Anna Salai Chennai-600 002.
3.Mr.G.Ashok Raj The Superintending Engineer, Thiruvannamalai Electricity Distribution Circle, Tamil Nadu Electricity Board/TANGEDCO 1/4
Thiruvannamalai, Thiruvannamalai District.
Contemnor(s) PRAYER Contempt Petition filed under Section1 11 of the Contempt of Courts Act, praying to punish the Respondents for disobediences of this Hon'ble High Court order dated 14.07.2025 made in W.P.No.25416 of 2025. For Petitioner:
Mr.M.R.Jothimanian For Respondents:
Mr.C.Manoharan Standing Counsel (TNEB) *****
ORDER
The Contempt Petition is filed to punish the respondent for the alleged wilful disobedience of the order issued by this Court on 14.07.2025 in WP.No.25416 of 2025.
2.Heard the learned counsel appearing for the petitioner and the learned Standing Counsel appearing for the respondents. 3.The learned Standing Counsel for the respondents would submit that the directions of this Court has been complied with and a copy of the order has also been circulated to the learned counsel for the petitioner. 2/4
4.Recording the above submission of the learned Standing Counsel, this Contempt Petition is closed. However, if the petitioner has got any grievance against the final order passed by the respondents, he is at liberty to challenge the same.
22-01-2026 kmi Index:Yes Speaking order Internet:Yes 3/4
C.KUMARAPPAN J.
kmi CONT P No.24 of 2026 22-01-2026 4/4