← Library
Madras High CourtWP/5180/2026disposed of with direction

M.S. Thangavel Staff No J06173 v. The Managing Dirctor

2026-02-18Honourable Mr Justice M.Dhandapani5 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED : 18.02.2026 CORAM :

THE HONOURABLE MR.JUSTICE M.DHANDAPANI W.P.No.

of 202

1. M.S.Thangavel

2. M. Mohamed Mubarack Ali

3. H. Devaraj Chalise

4. S. Rangasamy ...

Petitioners Vs

1. The Managing Director Tamil Nadu State Transport Corporation 37 Mettupalayam Road Coimbatore 641 043.

2. The General Manager Tamil Nadu State Transport Corporation Erodee Region, Chennimalai Road Erode 1.

3. The Administrator Tamil Nadu State Transport Corporation EPF Trust Pallavan House Thiruvalluvar Salai Chennai 600 002.

...

Respondents Prayer: Writ Petition filed under Article 226 of the Constitution of India, for Page No. 1 of 5

the issuance of a Writ of mandamus to direct the respondents to pay interest for the belated payment of Provident Fund, Gratuity, Encashment of Earned Leave, Surrender Leave and commuted value of pension at the rate of 12% p.a., within the time frame fixed by this Court. For Petitioners : Mr.N.Senthil Kumar For Respondents : Mr.M.Murali Vinoth - - - - -

ORDER

Aggrieved by the belated payment of terminal benefits and pension benefits such as Provident Fund, Gratuity, Encashment of Earned Leave, Surrender Leave and commuted value of pension, the petitioners have come up with this writ petition seeking interest at the rate of 12% per annum, for the said delay caused on the part of the respondents.

2. In view of the consent expressed by the learned counsel on either side, this writ petition is taken up for final disposal at the admission stage itself.

3. When the matter is taken up for hearing, the learned counsel for the petitioner brought to the notice of this Court, the order passed by the Coordinate Bench of this Court in a similar matter in W.P.No.25610 of 2024 dated 03.09.2024, wherein this Court had directed the respondent to pay Page No. 2 of 5

interest at the rate of 6% p.a. for the belated payment of terminal benefits to the petitioner therein within a period of six (6) weeks from the date of receipt of a copy of the order.

4. Learned counsel appearing for the 1st respondent did not dispute the above submission made by the learned counsel for the petitioners.

5. This Court perused the order passed in W.P.No.25610 of 2024, wherein, this Court has held as under :

"5.Taking into consideration the facts and circumstances of the case and the grievance expressed by the petitioner, there shall be a direction to the respondent to pay interest at the rate of 6% p.a. for the belated payment of terminal benefits to the petitioner within a period of six (6) weeks from the date of receipt of a copy of this order. It is made clear that if the amount is not paid within the time frame fixed by this Court, it will fetch interest at the rate of 12% p.a. from the date on which the amount became due and payable till the date of actual realisation."

6. The aforesaid decision is squarely applicable to the facts of the present case. Accordingly, applying the ratio laid down in the above case, this Page No. 3 of 5

writ petition is disposed of with a direction to the 1st respondent to pay interest at the rate of 6% p.a. for the belated payments viz. Provident Fund, Gratuity, Encashment of Earned Leave, Surrender Leave and commuted value of pension to the petitioners, within a period of six weeks from the date of receipt of a copy of this order. No costs. 18.02.2026 vsi2 Index: Yes/No To

1. The Managing Director Tamil Nadu State Transport Corporation 37 Mettupalayam Road Coimbatore 641 043.

2. The General Manager Tamil Nadu State Transport Corporation Erodee Region, Chennimalai Road Erode 1.

3. The Administrator Tamil Nadu State Transport Corporation EPF Trust Pallavan House Thiruvalluvar Salai Chennai 600 002.

Page No. 4 of 5

M.DHANDAPANI, J vsi2 W.P.No.5180 of 2026 18.02.2026 (2/2) Page No. 5 of 5