M/S. M.S.V.Construction, v. The Chief Engineer,
2025:MHC:2879
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 12.12.2025
CORAM
THE HONOURABLE MR. JUSTICE N. SATHISH KUMAR & W.M.P.Nos.54560 and 54562 of 2025 M/s.M.S.V.Construction Rep. By its Managing Director M.S.Veereppan Melsathampur Post Nadanthai (Via) Paramathi-Velur Taluk Namakkal District - 637 207 .. Petitioner
Versus
1. The Chief Engineer National Highways HRS Campus No.76, Sardar Pattel Road Guindy, Chennai - 600 025
2. The Superintending Engineer National Highways Omalur Main Road Narasothipatty
3. The Divisional Engineer National Highways Omalur Main Road Narasothipatty 1 / 4
. Respondents Prayer: Writ Petition is filed under Article 226 of the Constitution of India praying to issue a Writ of Mandamus directing the third respondent to issue work site inspection certificate and working condition of the plaints and machinery certificate to the petitioner for the tender notification in Tender Notice No.17/HDO/NH/2025-26 dated 02.12.2025 passed by the second respondent forthwith.
For Petitioner : Mr.N.Palanisamy For Respondents : Mr.Yogesh Kannadasan Special Government Pleader for R1 to R3
ORDER
The petitioner seeks a direction to the third respondent to issue work site inspection certificate to the petitioner for the tender notification in Tender Notice No.17/HDO/NH/2025-26 dated 02.12.2025.
2. The learned counsel for the petitioner submitted that the petitioner made spot inspection of the site and is owning all the required machineries, vehicles and other necessary equipments for the execution of the tender work and therefore, the petitioner submitted a representation dated 09.12.2025 seeking Site Inspection Certificate, but till date said certificate has not been issued to the petitioner. Hence, the present writ petition.
2 / 4
3. Mr.Yogesh Kanndasan, learned Special Government Pleader, who accepted notice on behalf of the respondents submits, on instructions, that the application of the petitioner will be processed and Work Site Inspection Certificate will be issued on 15.12.2025.
4. Recording the above submission of the learned Special Government Pleader, this writ petition stands disposed of. Consequently, the connected miscellaneous petitions are closed. There shall be no order as to costs.
12.12.2025 Index :Yes/No :Yes/No gpa To
1. The Chief Engineer National Highways HRS Campus,No.76, Sardar Pattel Road Guindy, Chennai - 600 025
2. The Superintending Engineer National Highways Omalur Main Road Narasothipatty
3. The Divisional Engineer National Highways Omalur Main Road Narasothipatty 3 / 4
N. SATHISH KUMAR , J.
gpa W.P.No.48860 of 2025 12.12.2025 4 / 4