Solaiappan Constructions v. Divisional Engineer
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED: 15-12-2025
CORAM
THE HONOURABLE MR JUSTICE N. SATHISH KUMAR Solaiappan Constructions Mg. Partner Satheesh Kumar Palanisamy, Door No. 232 Rana Nagar, Bhavani 638 301, Erode District.
Petitioner(s) Vs
1. Divisional Engineer National Highways, Gobichettipalayam Division, Gobichettipalayam.
2.Superintending Engineer National Highways, Salem Circle, Salem 4.
Respondent(s) PRAYER This writ petition filed under Article 226 of the Constitution of India Directing the 1st respondent to furnish work Site Inspection Certificate and Working Condition of Plants and Machineries as per the condition stipulated in the Tender Notice No.21/2025-26/ HDO/NH dated 3.12.2025 of the 2nd respondent inviting percentage Bids under Two Cover system immediately, in any event much before 16.12.2025 so as to submit to 2nd Respondent with Tender Application as stipulated and render justice. 1 / 4
For Petitioner(s):
Mr. VT. Narendiran Mr. A.T.Rajaprabhu For Respondent:
Mr. V.Jeevagiridharan AGP, for R1 & R2
ORDER
This writ petition has been filed seeking a direction to the first respondent to furnish the Work Site Inspection Certificate and the Working Condition of the Plants and Machinery Certificate to the petitioner in respect of the tender notification issued by the 2nd respondent vide No.21/2025-2026/HDO/NH dated 03.12.2025.
2. It is the contention of the petitioner that as per the tender conditions, the Worksite Inspection Certificate ought to have been issued on or before 16.12.2025 and the same has to be uploaded on the next day. Though the petitioner submitted a representation dated 10.12.2025 the inspection has not been conducted and Certificate has not been issued. Hence, the petitioner is before this Court.
3. The learned Additional Government Pleader appearing for the respondents, on instructions, would submit that Work Site Inspection Certificate and working Conditions of the Plants and Machinery Certificate will be issued 2 / 4
to the petitioner tomorrow, i.e.,16.12.2025 forenoon without fail.
4. The said submission of the learned Additional Government Pleader is recorded.
5. In such view of the matter, the first respondent shall issue the certificates to the petitioner as undertaken before this court.
6. With the above directions, this Writ petition is disposed of. No costs. 15-12-2025 Speaking/Non-speaking order Internet:Yes mrp To 1.Divisional Engineer National Highways, Gobichettipalayam Division, Gobichettipalayam.
2.Superintending Engineer National Highways, Salem Circle, Salem 4.
3 / 4
N.SATHISH KUMAR J.
mrp 15-12-2025 4 / 4