← Library
Madras High CourtWP/50235/2025disposed of with direction

E.Sekar v. The Managing Director

2026-01-05Honourable Mr Justice M.Dhandapani6 pages

IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 05.01.2026

CORAM:

THE HON'BLE MR.JUSTICE M.DHANDAPANI 1.E.Sekar 2.N.Kumaresan 3.A.Moses 4.K.Viswanathan

...Petitioners

Vs.

1.The Managing Director, Tamil Nadu State Transport Corporation Limited, No.2, Thiruvalluvar Illam, Anna Salai, Chennai - 600 002.

2.The Administrator, Tamil Nadu State Transport Corporation Employees' Pension Fund Trust, No.2, Pallavan Salai, Chennai - 600 002.

...Respondents

Writ Petition filed under Article 226 of the Constitution of India, to issue a Writ of Mandamus directing the respondents to pay interest of 10% to the petitioners for the belated payment of Gratuity, Leave Salary, Provident Fund and commutation of pension amounts. For Petitioners : Mr.S.Sakthivel 1/6

For respondent 1 : Mr.S.Sivasubramani For respondent 2 : Mr.C.S.K.Sathish

ORDER

Aggrieved by the belated payment of terminal benefits such as Gratuity, Leave Salary, Provident Fund and commutation of pension, the petitioners have come up with this Writ petition seeking interest at the rate of 10% per annum, for the said delay caused on the part of the respondents.

2. In view of the consent expressed by the learned counsel on either side, this Writ petition is taken up for final disposal at the admission stage itself.

3. When the matter is taken up for hearing, the learned counsel for the petitioners brought to the notice of this Court, the order passed by the Coordinate Bench of this Court in a similar matter in W.P.No.25610 of 2024 dated 03.09.2024, wherein this Court had directed the respondent to pay interest at the rate of 6% p.a. for the belated payment of terminal benefits to the petitioner therein within a period of six (6) weeks from the date of receipt of a copy of the order.

2/6

4. Learned counsel appearing for the respondents did not dispute the above submission made by the learned counsel for the petitioner.

5. This Court perused the order passed in W.P.No.25610 of 2024, wherein, this Court has held as under :- "5. Taking into consideration the facts and circumstances of the case and the grievance expressed by the petitioner, there shall be a direction to the respondent to pay interest at the rate of 6% p.a. for the belated payment of terminal benefits to the petitioner within a period of six (6) weeks from the date of receipt of a copy of this order. It is made clear that if the amount is not paid within the time frame fixed by this Court, it will fetch interest at the rate of 12% p.a. from the date on which the amount became due and payable till the date of actual realisation."

6. The aforesaid decision is squarely applicable to the facts of the present case. Accordingly, applying the ratio laid down in the above case, this Writ petition stands disposed of with a direction to the respondents to pay interest at the rate of 6% p.a. for the belated payment of Gratuity, Leave Salary, Provident Fund and commutation of pension amount to the 3/6

petitioners within a period of eight (8) weeks from the date of receipt of a copy of this order. There shall be no order as to costs. 05.01.2026 vm Index : Yes/No Speaking order : Yes/No NCC : Yes/No 4/6

To:

1.The Managing Director, Tamil Nadu State Transport Corporation Limited, No.2, Thiruvalluvar Illam, Anna Salai, Chennai - 600 002.

2.The Administrator, Tamil Nadu State Transport Corporation Employees' Pension Fund Trust, No.2, Pallavan Salai, Chennai - 600 002.

5/6

M.DHANDAPANI, J.

vm 05.01.2026 6/6