IN THE HIGH COURT OF JUDICATURE AT MADRAS

DATED: 26-12-2025

CORAM

THE HONOURABLE MR.JUSTICE V. LAKSHMINARAYANAN and W.M.P.No.56474 of 2025 M/s.Senbagam Constructions Rep. by its Managing Partner,K.Kuppusamy, 15, Perumal Pudhur, Kodumudi Main Road, Muthur, Tiruppur, Tamil Nadu, 638 105.

Petitioner(s) Vs

1. State of Tamil Nadu Rep. by its Secretary to government, Highways and Minor Ports Department, Fort St. George, Secretariat, Chennai- 600 009.

2.The Superintending Engineer Highways (Construction and Maintenance), Salem Circle, Omalur Main Road, Salem-636 004.

3.The Divisional Engineer Highways (Construction and Maintenance), No.6, Ram Nagar, 2nd Cross Street, Veerapandi Village, Gobichettipalayam-638 452.

Respondent(s) 1/5

PRAYER Writ Petition filed under Article 226 of the Constitution of India, praying to issue a Writ of Mandamus, directing the 3rd Respondent to issue the "Work Site Inspection Certificate" and "Certificate for working condition of the Plant and Machineries" as envisaged in Clause 11 and Clause 12 of the Tender Notice No.18/2025- 26/HDO/NH/Date: 03.12.2025 issued by the 2nd Respondent, based on the application dated 11.12.2025, 13.12.2025 and 22.12.2025 filed by the petitioner with the 3rd respondent for the work bearing Job No.TN- CRIF- 2025-26 -GBI- 25, on or before 30.12.2025 by 17.45 Hrs, so as to enable the petitioner to upload the same and participate in the bidding process.

For Petitioner(s):

Ms.J.Aparna For Respondent:

Mr.M.Bindran Additional Government Pleader (For R1)

ORDER

Heard Ms.Aparna, learned counsel for the petitioner and Mr.M.Bindran, learned Additional Government Pleader for the first respondent.

2. The petitioner has come forward with the writ petition seeking issuance of site inspection and working condition of plant and machinery certificates. The petitioner had approached the respondents by way of three representations dated 11.12.2025, 13.12.2025 and 22.12.2025. As none of them have elicited any response, he is before this Court.

2/5

3. When the matter was called, Mr.Bindran states that after verification of machineries as well as the other requirements, site inspection certificate and the working condition of plant and machinery certificate will be issued by 02.01.2026.The said instruction is scanned and extracted hereunder: 3/5

4. Recording the statement, the writ petition is disposed of. Consequently, connected miscellaneous petition is closed. There shall be no order as to costs. 26-12-2025 kak/mmi Index:Yes/No To

1. State of Tamil Nadu Rep. by its Secretary to government, Highways and Minor Ports Department, Fort St. George, Secretariat, Chennai- 600 009.

2.The Superintending Engineer Highways (Construction and Maintenance), Salem Circle, Omalur Main Road, Salem-636 004.

3.The Divisional Engineer Highways (Construction and Maintenance), No.6, Ram Nagar, 2nd Cross Street, Veerapandi Village, Gobichettipalayam-638 452.

4/5

V.LAKSHMINARAYANAN J.

kak 26-12-2025 5/5