← Library
Madras High CourtWP(MD)/449/2022disposed of

Inbaraj .S v. The Superintending Engineer

2025-10-28Honourable Mr Justice Abdul Quddhose5 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 28.10.2025

CORAM

THE HON'BLE MR.JUSTICE ABDUL QUDDHOSE S.Inbaraj : Petitioner Vs.

1.The Superintending Engineer, Highways Department, Madurai.

2.The Divisional Engineer, Highways Department, Construction and Maintenance, Palani, Dindigul District.

3.The Assistant Divisional Engineer, Highways Department, Construction and Maintenance, Vedasanthur, Dindigul District.

: Respondents 1/5

PRAYER: Writ Petition filed under Article 226 of the Constitution of India, to issue a Writ of Mandamus, directing the second respondent to consider the petitioner's representation dated 05.10.2017 which was forwarded by the third respondent in proceedngs in Na.Ka.No. 360/2018/E.Ni.U dated 13.11.2018 to the second respondent for promoting the petitioner as Road Inspector Grade - I, from the post of Road Inspector Grade-II in the second respondent Division. For Petitioner : Mr.V.Karuna For Respondents : Mr.A.Baskaran, Additional Government Pleader

O R D E R

This Writ Petition has been filed for a Mandamus seeking for a direction to consider the petitioner's representation dated 05.10.2017.

2.Learned Additional Government Pleader appearing for the respondents has placed on record the proceedings dated 29.02.2024 of the respondents and would submit that the representation of the petitioner dated 05.10.2017, has been duly 2/5

considered and final orders have been passed. A copy of the final order dated 29.02.2024 has also been given to the learned Counsel for the petitioner.

3.Since the representation of the petitioner dated 05.10.2017, which is subject matter of this Writ Petition has been considered and final orders passed on 29.02.2024, by the respondents, this Writ Petition is disposed of, by granting liberty to the petitioner to challenge the final order dated 29.02.2024, in the manner known to law, if the petitioner so desires. There shall be no order as to costs.

28.10.2025 Index :Yes / No Internet : Yes / No NCC : Yes/No MR 3/5

To 1.The Superintending Engineer, Highways Department, Madurai.

2.The Divisional Engineer, Highways Department, Construction and Maintenance, Palani, Dindigul District.

3.The Assistant Divisional Engineer, Highways Department, Construction and Maintenance, Vedasanthur, Dindigul District.

4/5

ABDUL QUDDHOSE.

, J.

MR 28.10.2025 5/5