BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT Dated : 04/02/2026
CORAM
THE HONOURABLE MR. JUSTICE R.VIJAYAKUMAR K. Rajendhiran, ... Petitioner Vs
1. The Superintending Engineer, Tangedco, Ramanathapuram, Ramanathapuram District..
2. The Executive Engineer, Tangedco, Paramakudi, Ramanathapuram District..
3. The Assistant Executive Engineer, Tangedco, Parthibanoor, Ramanathapuram District..
4. Samsudeen, S/o.Daavidhu,
5. Mohammed Najim, S/o.Daavidhu, ... Respondents PRAYER :- Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus to direct the 1/5
respondents 1 to 3 to shift the electricity poll and wire connection goes through the petitioner's house site plot which provides connection to the 4th respondent property and relocate the same without any disturbance to the petitioner's land lying in Survey No.251/43A2 and new Patta No. 9758, which is situated at Mela Parthibanoor, Parthibanoor Post, Paramakudi Taluk, Ramanathapuram District within stipulated time fixed by this Court.
For Petitioner : Mr.P. Ranjith Kumar For R1 to R3 : Mr.S.Deena Dhayalan Standing Counsel For R4 : Mr.P.Venkatasubramanian
ORDER
The present writ petition has been filed seeking a Writ of Mandamus directing the respondents 1 to 3 to shift the electricity pole and wire connection goes through the petitioner's house site and relocate the same without any disturbance to the petitioner's land in Survey No. 251/43A2 and new Patta No.9758, which is situated at Mela Parthibanoor, Parthibanoor Post, Paramakudi Taluk, Ramanathapuram District.
2/5
2. According to the learned counsel appearing for the writ petitioner, even though the electricity poll is outside his property, the electrical lines are running through his property, which are obstructing construction activities. Since he wants to put up the construction on the property, he made a representation to the respondents for relocating the same. However, the said request has been rejected by the fourth respondent on the ground that the electricity service connections are being drawn only through the said pole.
3. The learned Standing Counsel appearing for the respondents 1 to 3 submitted that if the petitioner makes any fresh application under DWC Scheme, depending upon feasibility, the relocation of the electricity pole would be considered.
4. It is made clear that the service connection to the fourth respondent's property should not be affected in any manner. 3/5
5. In view of the above, this writ petition stands disposed of with a direction to the writ petitioner to file an appropriate application to the respondents 1 to 3 under the DWC scheme. Based upon the application, the respondent 1 to 3 are directed to proceed in accordance with law, depending on the outcome of the feasibility report. The said exercise shall be completed within a period of 12 weeks from the date of receipt of a copy of this order. No Costs.
04.02.2026 TTA TO
1. The Superintending Engineer, Tangedco, Ramanathapuram, Ramanathapuram District..
2. The Executive Engineer, Tangedco, Paramakudi, Ramanathapuram District..
3. The Assistant Executive Engineer, Tangedco, Parthibanoor, Ramanathapuram District..
4/5
R.VIJAYAKUMAR,J TTA
ORDER
IN WP(MD) No.1539 of 2025 Date : 04/02/2026 5/5