Tamilarasan.R v. The Superintending Engineer
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 05.02.2024
CORAM
THE HONOURABLE MRS.JUSTICE V.BHAVANI SUBBAROYAN R.Tamilarasan ... Petitioner -Vs1.The Superintending Engineer, Pudukottai Distribution Circle (North), Tamil Nadu Generation & Distribution Corporation Ltd., (TANGEDCO), Pudukkottai - 622 001.
2.The Executive Engineer (Gen), Pudukkottai Distribution Circle (North), Tamil Nadu Generation & Distribution Corporation Ltd., (TANGEDCO), Pudukkottai - 622 001.
3.The Assistant Executive Engineer, Pudukkottai Distribution Circle (North), Tamil Nadu Generation & Distribution Corporation Ltd., (TANGEDCO), Pudukkottai - 622 001.
... Respondents PRAYER:- Writ Petition is filed under Article 226 of the Constitution of India, praying for the issuance of a Writ of Mandamus directing the respondents to provide electricity service connection to the petitioner's 1/5
house situated in T.S.No. 7785/5C in Block No.131, Balaji Nagar (Malayappa Nagar), Pitchathanpatti, Pudukottai Town, by considering the petitioner's application dated 25.01.2023 and petitioner's further representation dated 03.06.2023.
For Petitioner : Mr.H.Mahamed Hussain For Respondents : Mr.S.Deenadhayalan
ORDER
This writ petition is filed seeking for issuance of a Writ of Mandamus directing the respondents to provide electricity service connection to the petitioner's house situated in T.S.No. 7785/5C in Block No.131, Balaji Nagar (Malayappa Nagar), Pitchathanpatti, Pudukottai Town, by considering the petitioner's application dated 25.01.2023 and his further representation dated 03.06.2023.
2. It is seen that the petitioner's gave an application dated 25.01.2023 to the respondents for the new electricity service connection to his house. Thereafter, he made a representation dated 03.06.2023 to the respondents. Since the said representation and the application have not been considered so far, the petitioner has filed the present writ petition. 2/5
3. Mr.S.Deenadhayalan, learned Standing Counsel appearing for the respondent would submit that in respect of the petitioner's property, there is a civil suit pending, hence, the respondents have not considered the case of the petitioner. However, the learned Standing Counsel would submit that if the petitioner has filed an indemnity bond, the respondents will take steps to provide electricity service connection, otherwise, problem will arose.
4. In view of the above, the petitioner is directed to file the indemnity bond and after receiving the indemnity bond, the respondents shall provide electricity service connection to the petitioner's house by following the procedures.
5. With the above direction, the writ petition stands disposed of. No costs.
05.02.2024 NCC : Yes/No Index : Yes/No Internet : Yes skn 3/5
To 1.The Superintending Engineer, Pudukottai Distribution Circle (North), Tamil Nadu Generation & Distribution Corporation Ltd., (TANGEDCO), Pudukkottai - 622 001.
2.The Executive Engineer (Gen), Pudukkottai Distribution Circle (North), Tamil Nadu Generation & Distribution Corporation Ltd., (TANGEDCO), Pudukkottai - 622 001.
3.The Assistant Executive Engineer, Pudukkottai Distribution Circle (North), Tamil Nadu Generation & Distribution Corporation Ltd., (TANGEDCO), Pudukkottai - 622 001.
4/5
V.BHAVANI SUBBAROYAN, J.
skn 05.02.2024 5/5