← Library
Madras High CourtCONT P(MD)/225/2020closed

M/S.Koya And Company Construction Limited v. P.Ramachandran

2020-10-07Honourable Mr Justice G.R.Swaminathan3 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 07.10.2020

CORAM:

THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN in W.P.(MD)No.6409 of 2019 M/s.Koya & Company Construction Limited, Rep.by its Project Manager, A.Ravikumar, No.72, MIGH, Mehadipatnam, Hyderabad - 500 028.

... Petitioner Vs.

1.P.Ramachandran, The Chief Engineer, TWAD Board, Ganesh Nagar, Near Law College Hostel, Opp.Mattuthavani Bus Stand, Melur Road, Madurai - 625 007.

2.Viswalingam The Executive Engineer, TWAD Board, Urban Division, 62/8, Second Floor, New Road, Kovilpatti - 628 501.

3.G.Kathiresan, The Executive Engineer, TWAD Board, Project Division, Jawahar 3rd Street, Nagercoil.

4.Dr.C.N.Mahesvaran, Managing Director, Tamil Nadu Water Supply and Drainage Board, No.31, Kamarajarsalai, Chepauk, Chennai - 5.

... Respondents/Contemnors Prayer: Contempt Petition filed under Section 11 of the Contempt of Courts Act, 1971, to punish the respondent for the deliberate and willful disobedience of the order passed by this Court in W.M.P.(MD) No.5125 of 2019 in W.P.(MD)No.6409 of 2019, dated 19.03.2019. Prayer in WP(MD).6409/ 2019 :

Writ Petition is filed under Article 226 of the Constitution of India, praying this Court to issue a writ of Certiorari calling for the records relating to the impugned order

passed by the 2nd respondent in his proceedings Lr.No.F.Kovilpatti WSIS/JDO/2016/dated 02.03.2019 and quash the same as illegal and arbitrary.

Prayer in WMP(MD). 5125/ 2019 :

Petition praying that in the circumstances stated therein and in the affidavit filed therewith the High Court will be pleased to grant an order of Interim Stay of the operations and all further proceedings of the impugned order passed by the 2nd respondent in his proceedings Lr.No.F.Kovilpatti WSIS/JDO/2016/dated 02.03.2019, pending disposal of the above writ petition.

For Petitioner : Mr.B.Saravanan For Respondents : Mrs.Porkodikarnan

O R D E R

When the matter was taken up for hearing, the learned counsel on either side stated that the order dated 19.03.2019 passed by this Court has been complied with.

2. Recording the said submission, this Contempt petition is closed.

Sd/- Assistant Registrar (CS-II) // True Copy // / /2020 Sub Assistant Registrar(CS) das Note : In view of the present lock down owing to COVID-19 pandemic, a web copy of the order may be utilized for official purposes, but, ensuring that the copy of the order that is presented is the correct copy, shall be the responsibility of the advocate/litigant concerned.

To 1.The Chief Engineer, TWAD Board, Ganesh Nagar, Near Law College Hostel, Opp.Mattuthavani Bus Stand, Melur Road, Madurai - 625 007.

2.The Executive Engineer, TWAD Board, Urban Division, 62/8, Second Floor, New Road, Kovilpatti - 628 501.

3.The Executive Engineer, TWAD Board, Project Division, Jawahar 3rd Street, Nagercoil.

4.Managing Director, Tamil Nadu Water Supply and Drainage Board, No.31, Kamarajarsalai, Chepauk, Chennai - 5.

in W.P.(MD)No.6409 of 2019 07.10.2020 SCR(CO) CS(14.10.2020) 3P 5C