BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 16.02.2024

CORAM:

THE HONOURABLE MR.JUSTICE D.KRISHNAKUMAR AND THE HONOURABLE MR.JUSTICE R.VIJAYAKUMAR W.P.(MD)No.3610 of 2024 J.Mercy Jebamani ... Petitioner -Vs1.The District Collector, Collectorate, Dindigul.

2.The Divisional Engineer, National Highways Authority of India, Dindigul.

3.The Project Director, National Highways Authority of India, No.1, Aishwarya Apartments, 1st Street, Indira Nagar, Sennamanaickenpatti Post, Thadikombu Road, Dindigul.

4.The Independent Engineer, S.A.Infrastructure Consultants Pvt Ltd., Thiruvalluvar Salai, Shanmugapuram, Palani, Dindigul District.

5.The Authorized Signatory, M/s.KNR Constructions Ltd., Puliampatti, Palani Taluk, Dindigul District. ... Respondents

PRAYER: Petition filed under Article 226 of the Constitution of India, to issue a Writ of Mandamus, to direct the respondents 2 and 3 to connect the Rukkuvarpatti service road with NH-209 (New NH-83) by considering the communication in NHAI/PIU/DGL/11014/General/NH-209/PCK II/2023/2544, dated 24.11.2023 within a time that may be stipulated by this Court. For Petitioner : Mr.N.Mohan For R1 & R2 : Mr.P.Thilak Kumar, Government Pleader For R3 : Mr.P.Karthick

ORDER

[Order of the Court was made by D.KRISHNAKUMAR, J.] This Writ Petition is filed to direct the respondents 2 and 3 to connect the Rukkuvarpatti service road with NH-209 (New NH-83) by considering the communication in NHAI/PIU/DGL/11014/General/NH-209/PCK II/2023/2544, dated 24.11.2023 within a time that may be stipulated by this Court. 2.By consent of both parties, this Writ Petition is taken up for final disposal at the stage of admission itself.

3.Mr.P.Thilak Kumar, learned Government Pleader takes notice for the respondents 1 and 2 and Mr.P.Karthick, learned counsel takes notice for the 3rd

respondent. Considering the nature of order going to be passed in this Writ Petition, notice to the respondents 4 and 5 is dispensed with. 4.The petitioner's grievance is that his representation dated 21.11.2023 to connect the Rukkuvarpatti service road with NH-209 (New NH-83), has not been considered so far. Hence, he has filed this Writ Petition. 5.Considering the facts and circumstances of the case, without going into the merits of the case, we direct the 3rd respondent to consider the petitioner's representation dated 21.11.2023 and pass appropriate orders on its own merits and in accordance with law within a period of twelve weeks from the date of receipt of a copy of this order.

6.With the above direction, this Writ Petition stands disposed of. No costs.

[D.K.K., J.] & [R.V., J.] 16.02.2024 NCC : Yes / No Index : Yes / No Internet : Yes / No Yuva

D.KRISHNAKUMAR, J.

AND R.VIJAYAKUMAR , J.

Yuva To 1.The District Collector, Collectorate, Dindigul.

2.The Divisional Engineer, National Highways Authority of India, Dindigul.

3.The Project Director, National Highways Authority of India, No.1, Aishwarya Apartments, 1st Street, Indira Nagar, Sennamanaickenpatti Post, Thadikombu Road, Dindigul.

W.P.(MD)No.3610 of 2024 16.02.2024