Elavarasan. G v. The Principal Secretary
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 09.04.2021
CORAM
THE HONOURABLE MR.JUSTICE N.ANAND VENKATESH G.Elavarasan .. Petitioner Vs.
1.The Principal Secretary, Public Work Department, St. George Fort, Secretariat, Chennai - 600 009.
2.The Chief Engineer, Madurai Zone, Madurai - 625 002.
3.The Superintend Engineer, Periyar Vaigai Basin Circle, Madurai - 625 001.
.. Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India, praying to issue a Writ of Mandamus, directing the respondents to consider the petitioner's representation dated 18.02.2021 and 24.02.201 regarding bid application for the Tender Reference No.NIT 11/D2/C.135/2020/Date 25.01.2021 and Tender ID:pwd181808.
For Petitioner : Mr.R.Selvaraj For Respondents : Mr.D.Muruganantham, Addl. Govt. Pleader *****
ORDER
This Writ Petition has been filed for the issue of a Writ of Mandamus, directing the respondents to consider the representation made by the petitioner on 18.02.2021, and to accept the tender application submitted by the petitioner.
1/3
2. The learned Additional Government Pleader, on instructions, submitted that the tender application submitted by the petitioner was received beyond time and therefore, his application was not considered and it was returned. It was further submitted that the tender has already been finalized and the work order has also been issued and therefore, nothing survives in this Writ Petition.
3. Taking into consideration the subsequent development that has taken place in this case, no further orders can be passed in this Writ Petition. If the petitioner is aggrieved in the manner in which the tender process was conducted and allotted in favour of the successful bidder, a separate writ petition has to be filed challenging the same. Except giving this liberty, no further orders can be passed in this Writ Petition.
4. This writ petition is disposed of accordingly. No costs. Sd/- Assistant Registrar () // True Copy // / /2021 Sub Assistant Registrar(CS) Note :
In view of the present lock down owing to COVID-19 pandemic, a web copy of the order may be utilized for official purposes, but, ensuring that the copy of the order that is presented is the correct copy, shall be the responsibility of the Advocate / litigant concerned.
To 1.The Principal Secretary, Public Work Department, St. George Fort, Secretariat, Chennai - 600 009.
2.The Chief Engineer, Madurai Zone, Madurai - 625 002.
2/3
3.The Superintend Engineer, Periyar Vaigai Basin Circle, Madurai - 625 001.
+1 CC to M/s.SPL GP ( SR-15854[F] dated 15/04/2021 ) 09.04.2021 Ak(26/02/2021) 3 P 5C 3/3