Pandi. V v. The District Collector
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED:17.04.2026
CORAM
THE HONOURABLE MR.JUSTICE HEMANT CHANDANGOUDAR V.Pandi ..
Petitioner - Vs. -
1. The District Collector, Madurai District, Madurai.
2. The District Revenue Officer, East Taluk, Madurai.
3. The Revenue Divisional Officer, Melur, Vellaripatti, Madurai.
4. The Tahsildar, Madurai East, Arumpanur Village, Y.Othakadai, Madurai.
5. The Block Development Officer, Madurai East, Madurai.
... Respondents 1/6
Prayer : Writ Petition is filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, directing the 5th respondent to remove the unauthorized/illegal Thar road in S.No. 93/9B at Arumbanoor II Pit, Arumbanoor Village, Madruai District on the basis of the representation dated 10.04.2023.
For Petitioner : Mr.Arunmozhi Rajashankar For Respondents : Mr. P.Subbaraj Special Government Pleader for R1 to R4 : Mr.A.K.Manikkam for R5
O R D E R
The petitioner is before this Court seeking for a direction to the respondents to remove the Government Thar Road in S.No.93/9B at Arambanoor II Pit, Arumbanoor Village, Madurai District.
2. The petitioner claims to be the joint owner of the S.No.93/9B-1 measuring to an extent of 0.23.70 ares. The petitioner states that the 2/6
respondents without following due process of law has laid the Government road which is in violation of Article 300 A of the Constitution of India.
3. The 5th respondent has filed counter affidavit stating that the Firka Surveyor, Arumbanur, has conducted a survey on 15.03.2024 and submitted a report stating that the said land jointly belongs to the petitioner and two other individuals and patta was assigned and patta bearing No. 406 was issued in their names and the Thar road is laid in the said land.
4. It is further stated that the Thar road serves as the public pathway enabling the people to travel from the nearby villages and the said road is the only access to Government Primary School, Primary Health Centre and E-Seva Centre, etc.,
5. It is further stated that the said road was upgraded to District Road Standards and handed over to Highways Department on 27.10.2017 and the road was laid in 2021 and currently the said road is under the 3/6
maintenance of the Highways Department.
6. In any event, the said land jointly belongs to the petitioner and two other individuals and the respondent before laying the Thar road on the said land ought to have followed due process of law. Without following due process of law, the respondent has laid the Thar road and the same is arbitrary and discriminatory.
7. Accordingly, the Writ Petition is disposed of directing the respondents to remove the unauthorized Thar road laid in S.No.93/9B-1 within a period of six(6) weeks from the date of receipt of a copy of this order.
8. There shall be no orders as to costs.
17.04.2026 Index :Yes / No NCC :Yes / No PJL 4/6
To
1. The District Collector, Madurai District, Madurai.
2. The District Revenue Officer, East Taluk, Madurai.
3. The Revenue Divisional Officer, Melur, Vellaripatti, Madurai.
4. The Tahsildar, Madurai East, Arumpanur Village, Y.Othakadai, Madurai.
5. The Block Development Officer, Madurai East, Madurai.
5/6
HEMANT CHANDANGOUDAR, J.
PJL 17.04.2026 6/6