BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 20.01.2026

CORAM:

THE HONOURABLE MR.JUSTICE R.VIJAYAKUMAR W.P(MD)No.3273 of 2023 and W.M.P(MD) No.3030 of 2023 1.Ansar Ali

2. R.Bajriammal

3. Jainalaudeen

4. Jameela Meharaj Banu ... Petitioners Vs.

1. The Executive Officer, Keeranur Selection Grade Town Panchayat, Pudhukottai District.

2. DCB Bank, Represented by its Branch Manager, Thillai Nagar Branch, Thiruchirapalli - 620 018.

... Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, directing the first respondent to grant the building plan approval pursuant to the petitioners' application dated 22.04.2022 without insisting for a No Objection Certificate from the second respondent in a time bound manner.

1/5

For Petitioner : Mr.S.Ramsundar Vijayraj For R1 : Mrs.D.Farjana Ghoushia Special Government Pleader For R2 : No appearance

O R D E R

The present writ petition has been filed seeking a Mandamus directing the first respondent to grant a building plan approval pursuant to the petitioners' application dated 22.04.2022 without insisting for "No Objection Certificate" from the second respondent.

2. A perusal of the records reveal that the petitioners have purchased the property under a registered sale deed, dated 07.07.2000. The petitioners have created a mortgage by depositing of title deeds with regard to the properties on 12.05.2016. Thereafter, the petitioners have made an application on 22.04.2022 seeking building plan approval. However, the application is kept pending before the first respondent on the ground that the petitioners should produce "No Objection Certificate" from the second respondent Bank. Therefore, the petitioners have filed the present writ petition. 2/5

3. The petitioners have mortgaged the vacant site with the second respondent Bank by depositing the title deeds on 12.05.2016. Putting up construction in the vacant site will only increase the value of the property. Therefore, the question of obtaining "No Objection Certificate" from the second respondent Bank does not arise.

4. In view of the above said facts, the petitioners are directed to represent their application seeking building plan approval and the same shall be considered without insisting for "No Objection Certificate" from the second respondent Bank and orders may be passed within a period of eight weeks from the date of receipt of a copy of this order.

5. With the above said observation, this writ petition stands disposed of. There shall be no order as to costs. Consequently connected Miscellaneous Petition is closed.

20.01.2026 NCC : Yes/No Index : Yes / No Internet : Yes / No ebsi 3/5

To

1. The Executive Officer, Keeranur Selection Grade Town Panchayat, Pudhukottai District.

2. DCB Bank, Represented by its Branch Manager, Thillai Nagar Branch, Thiruchirapalli - 620 018.

4/5

R.VIJAYAKUMAR,J.

ebsi W.P(MD)No.3273 of 2023 20.01.2026 5/5