Madras High CourtWP(MD)/5016/2021disposed of

Selvi v. The Superintending Engineer

2023-06-23Honourable Ms. Justice P.T. Asha4 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 23.06.2023

CORAM:

THE HONOURABLE MS.JUSTICE P.T.ASHA Selvi .. Petitioner Vs.

1.The Superintending Engineer, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Pudukottai.

2.The Executive Engineer, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Keeranur South, Keeranur Village & Post, Kulathur Taluk, Pudukottai District.

3.The Assistant Engineer, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Keeranur South, Keeranur Village & Post, Kulathur Taluk, Pudukottai District.

4.Paanchali 5.The Inspector of Police (Circle), Thirukokarnam Police Station, Pudukottai, Pudukottai District.

6.The Sub Inspector of Police, Vellanur Police Station, Vellanur, Pudukottai District.

.. Respondents Prayer :- Petition filed under Article 226 of the Constitution of India, praying for issuance of Writ of Mandamus, directing respondents 1 to 3 to forthwith complete the work of "Deviation of HT/LT lines" as per the petitioner's application Registration No.1620520139 dated 19.05.2020 and on the basis of the payment made on 18.06.2020 as per the Tamilnadu Electricity Distribution Standards of Performance Regulations, 2004 with the adequate police protection and aid of respondents 5 and 6.

For Petitioner :

Mr.J.Davit Ganeshan For RR1 to 3 :

Mr.S.Deenadhayalan Standing Counsel For R4 :

Mr.V.Sethumadhavan For R6 :

No appearance

ORDER

This writ petition is filed for the issue of a Writ of Mandamus, directing respondents 1 to 3 to forthwith complete the work of "Deviation of HT/LT lines" as per the petitioner's application

Registration No.1620520139 dated 19.05.2020 and on the basis of the payment made on 18.06.2020 as per the Tamilnadu Electricity Distribution Standards of Performance Regulations, 2004 with the adequate police protection and aid of respondents 5 and 6.

2. Though the petitioner has sought for shifting of the pole, learned counsel for the petitioner, on instructions from his client, would submit that the pole can be installed within the premises of the petitioner.

3. Recording the above, this Writ Petition is disposed of directing respondents 1 to 3 to complete the work within a period of four weeks from the date of receipt of a copy of this order or production of the copy of this order. No costs.

23.06.2023 NCC : Yes/No Index : Yes/No Internet : Yes abr

P.T.ASHA, J.

abr To 1.The Superintending Engineer, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Pudukottai.

2.The Executive Engineer, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Keeranur South, Keeranur Village & Post, Kulathur Taluk, Pudukottai District.

3.The Assistant Engineer, Tamilnadu Generation and Distribution Corporation Limited (TANGEDCO), Keeranur South, Keeranur Village & Post, Kulathur Taluk, Pudukottai District.

Dated: 23.06.2023