Anish Jalila v. The Tashildhar
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 29.02.2024
CORAM
THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN Anish Jalila ... Petitioner Vs.
1.The Tahsildar, Tahsildar Office, Kadaladi, Ramanathapuram District.
2.The Head Surveyor, Kadaladi, Ramanathapuram District.
3.The Inspector of Police, Kadaladi Police Station, Ramanathapuram District.
... Respondents Prayer : Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, to direct the 2nd respondent to survey, demarcate four boundaries of the petitioner's property situated in Survey No.348/7, Iruveli Village, Iruveli Group, Sayalkudi Sub-Division, Ramanathapuram District admeasuring 867 Sq. ft (80.27 Sq.Mts) bearing its Patta No.179 with the help of the police protection to be accorded by the 3rd respondent by considering the petitioner's petition No.
2023/9005/27/427998/1106 dated 06.11.2023.
1/5
For Petitioner : Mr.RL. Dhilipan Pandian For Respondents : Mr.V.Nirmal Kumar Government Advocate for R1 & R2 : Mr.A.Albert James Government Advocate (crl.side) for R3
ORDER
When the matter was taken up for hearing, the learned Additional Government Pleader submitted that on 07.03.2024, survey is proposed to be conducted. The following directions shall be borne in mind. 2.The Writ Petition is disposed of with the following directions:- (I) The survey authority will scrutinize if the application submitted by the petitioner is in order.
(II) The petitioner will have to enclose all the relevant documents such as patta. The applicant must have individual patta in his / her name. If he / she is having joint patta, co-pattadars must given their consent for conducting survey. (III) The survey authority will issue notice to the writ petitioner as well as the adjacent land owners and also to the interested persons, if any.
(IV) Enquiry shall be held. During enquiry, objections raised 2/5
by the adjacent land owners / interested persons shall be considered. (V) If according to the jurisdictional authority, the objections are without any basis, the same shall be overruled and the objectors shall be informed accordingly. But the survey will be conducted only after a period of six weeks so that the objector can move the concerned Court for injunction. If before the proposed date of survey, the objector is unable to obtain any injunction order, the survey can very well go on.
(VI) It is open to the parties to serve memo of instructions to the surveyor at the time of conducting survey. The same will be borne in mind. While it cannot be binding on the surveyor, the same will be taken note of.
(VII) If the jurisdictional authority finds objections to be having substance, then, he shall call upon the applicant to move the jurisdictional civil Court for agitating his rights. (VIII) If required, the survey authority is empowered to seek aid of the jurisdictional police and the jurisdictional police are mandated to grant police protection.
(IX) It is made clear that at the end of the survey exercise, survey stones alone can be installed. The exercise of survey and 3/5
demarcation undertaken pursuant to the direction of this Court can never result in dispossession of any party. No person shall put up fencing at the time of survey by using police aid. (X) The survey authority will conclude the entire exercise one way or the other within a period of six weeks after service of notice on the interested persons.
(XI) A copy of the survey report along with sketch will be served on the parties. No costs.
29.02.2024 Index : Yes / No Internet : Yes/ No rmi To 1.The Tahsildar, Tahsildar Office, Kadaladi, Ramanathapuram District.
2.The Head Surveyor, Kadaladi, Ramanathapuram District.
3.The Inspector of Police, Kadaladi Police Station, Ramanathapuram District.
4/5
G.R.SWAMINATHAN, J.
rmi 29.02.2024 5/5