THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN and W.M.P(MD)No.4700 of 2024 M.Rajendran ... Petitioner Vs.
1.The Secretary to Government, St.George Fort, Chennai.
2.The Chief Engineer, Chief Engineer's Office, HRS Campus, 76, Sardar Patel Road, Guindy, Chennai.
3.The District Collector, 4.The District Revenue Officer, Tirunelveli, Tirunelveli District.
5.The Superintendent Engineer, 1/6
Palayamkottai, 6.The Divisional Engineer, Palayamkottai, 7.The Special Tahsildar (Land Acquisition), Land Acquisition and Administration, O/o.1st Floor, Assistant Divisional Engineer Office (Highways), AR Line Road, Palayamkottai, 8.Sami (R.8 is suo motu impleaded vide order of this Court dated 04.03.2024) ... Respondents Prayer : Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, forbearing the respondents to lay the road at the petitioner's property in Survey No. 55/2 to the total extent of 1.05 acres situated at Kallidaikurichi North Village, Ambasamudram Taluk, Tirunelveli District without following due process of law.
For Petitioner : Mr.A.Sankararamasubramanian For Respondents : Mr.M.Lingadurai Special Government Pleader for R.1 to R.7 Mr.D.Saravanan for R.8 2/6
ORDER
Heard both sides.
2.The prayer in the writ petition is not maintainable for more than one reason. It has been convincingly demonstrated before me by the learned Special Government Pleader that the acquisition notification was already issued and it has become final also. This aspect of the matter was captured vide order dated 11.07.2022 in W.P(MD)No.12681 of 2012. Paragraphs 3 and 4 of the said order read as follows: "3. Admittedly, in the present case, a notification was issued for acquisition of land under Section 15(2) on 22.09.2014. The petitioners and other land owners were requested to submit their objections. Thereafter, after hearing the objections, the notification for acquisition of land was passed under Section 15(1) on 02.03.2016. According to the learned Counsel for the respondents, an award has been passed on 31.12.2001 and the acquired land has also been handed over to the highways on 31.03.2022.
3/6
4. The present writ petition has been filed in the year 2012, before a notification was issued under Section 15(2) of the Tamil Nadu Highway Act, 2001, under the presumption that the lands are likely to be acquired. Thereafter, actual acquisition proceedings have been followed and the lands of the petitioners have been acquired, an award has also been passed. The said acquisition proceedings or the award have not been challenged. Hence, nothing survives in the present writ petition. However, if the petitioner is aggrieved by the award, he is entitled to challenge the same in a manner known to law, with regard to the quantum of compensation."
The petitioner herein was the petitioner No.1 in the said writ petition. Therefore, I am not in a position to consider the plea made by the learned counsel appearing for the petitioner.
3.This writ petition stands dismissed. There shall be no order as to costs. Consequently, connected miscellaneous petition is closed. 04.03.2024 NCC : Yes/No Index : Yes / No Internet : Yes/ No MGA To 1.The Secretary to Government, 4/6
St.George Fort, Chennai.
2.The Chief Engineer, Chief Engineer's Office, HRS Campus, 76, Sardar Patel Road, Guindy, Chennai.
3.The District Collector, 4.The District Revenue Officer, Tirunelveli, 5.The Superintendent Engineer, Palayamkottai, 6.The Divisional Engineer, Palayamkottai, 7.The Special Tahsildar (Land Acquisition), Land Acquisition and Administration, O/o.1st Floor, Assistant Divisional Engineer Office (Highways), AR Line Road, Palayamkottai, G.R.SWAMINATHAN, J.
MGA 5/6