M/S.Arun Cooling Home v. The Superintending Engineer
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 12.03.2024
CORAM
THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN and W.M.P(MD)No.5628 of 2024 M/s.Arun Cooling Home, A Partnership Firm, Represented by its Partner, Kanaleeswaran, S/o.Duraisamy, No.24, Chittrakara Street, Madurai - 625 001.
... Petitioner Vs.
1.The Superintending Engineer, Madurai Electricity Distribution Circle, TANGEDCO, Madurai.
2.The Executive Engineer, Tirupalai, TANGEDCO, Madurai.
3.The Assistant Engineer, TANGEDCO, Alagarkovil, Madurai.
... Respondents Prayer : Writ Petition filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus, directing the 1/4
respondents to assess Current Consumption Charges to the petitioner's Electricity Service Connection No.05-109-008-2124 under tariff III B, in terms of Tamil Nadu Electricity Regulatory Commission Order dated 02.02.2021 made in TA No.1 of 2020 from the date of effecting service connection.
For Petitioner : Mr.R.Murali For Respondents : Mr.S.Deenadhayalan Standing Counsel
ORDER
When the matter was taken up for hearing, the learned Standing Counsel appearing for TANGEDCO clarified that if the petitioner submits an online application with all the relevant details, the petitioner would be accessed under Tariff III-B.
2.Recording the said submission, this writ petition is disposed of. There shall be no order as to costs. Consequently, connected miscellaneous petition is closed.
12.03.2024 NCC : Yes/No Index : Yes / No Internet : Yes/ No MGA 2/4
To 1.The Superintending Engineer, Madurai Electricity Distribution Circle, TANGEDCO, Madurai.
2.The Executive Engineer, Tirupalai, TANGEDCO, Madurai.
3.The Assistant Engineer, TANGEDCO, Alagarkovil, Madurai.
3/4
G.R.SWAMINATHAN, J.
MGA 12.03.2024 4/4