BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT Civil Appellate Jurisdiction Tuesday, the Nineteenth day of August Two Thousand and Twenty Five PRESENT THE HONOURABLE MR. JUSTICE M.DHANDAPANI CRP(MD). No.892 of 2023 G.Jebakumar Jebamani, ... Petitioner/ Petitioner Vs The Special Thasildhar (Land Acquisition) River Linking Project Unit III River Linking Palayamkottai Tirunelveli District. Respondent/Respondent Prayer :- Civil Revision Petition filed under Article 227 of Constitution of India, to pass appropriate orders directing the Principal District Judge, Tirunelveli to dispose of the LAOP.No. 120/2022 within the time stipulated by this Court. ORDER:- This Civil Revision Petition coming on for orders upon this day under the caption "Extension of time for Lower Court" and upon perusing earlier order of this Court dated 31.03.

2023 and the requisition letter submitted by the Principal District Judge Tirunelveli, in D.No.9055/2025 dated 17.07.2025 seeking further extension of time for disposal of the case in LAOP No.

This court, by order dated 31.03.2023, directed the Court below to dispose of the case in L.A.O.P.No.120 of 2022 within a period of twelve months from the date of receipt of copy of the order.

2. Thereafter, heeding to the request of the learned Principal District Judge, Tirunelveli, vide letter No.8974 dated 03.07.2024 for extension of time for the disposal of the case, this court by order dated 22.07.2024 granted further nine months' time from the date of receipt of copy of the order.

3. Now, the learned Principal District Judge, once again addressed a letter vide D.No.9055/2025, dated 17.07.2025 whereby and whereunder stating some reasons, he requested further nine months time to comply with the order dated 31.03.2023 and 22.07.2024 made in this Civil Revision Petition.

4. Considering the reasons stated by the Court below for extension of time, nine months time is extended from the date of receipt of a copy of this order to comply with the orders dated 31.03.2023 and 22.07.2024. Sd/- Assistant Registrar (CS-III) // True Copy // / /2025 Sub Assistant Registrar (CS - I/II/III/IV) TO

1. The Principal District Judge, Tirunelveli.

2. The Special Thasildhar (Land Acquisition) River Linking Project Unit III River Linking Palayamkottai Tirunelveli District.

Copy to:

The Section Officer, Judicial Section, Madurai Bench of Madras High Court, Madurai.

ORDER DATED : 19/08/2025 ========================== EXT OF TIME ========================== CRP(MD). No.892 of 2023 Giving direction and etc.

as stated within.

TS (03/09/2025) 3P/4C Madurai Bench of Madras High Court is issuing certified copies in this format from 17.07.2023.