BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 13.02.2017 CORAM :

THE HONOURABLE MR.JUSTICE S.VAIDYANATHAN W.P(MD)No.18455 of 2014 S.T.Rengarajan ... Petitioner vs.

1)The Government of TamilNadu, Rep. by its Principal Secretary, Highways Department, Fort St.George, Secretariat, Chennai-600 009.

2)The Chief Engineer(H), Designs and Investigation, Block 3, Second floor, SIDCO Electronics Complex, Thiru-vi-ka Industrial Estate, Guindy, Chennai-600 032.

3)The Divisional Engineer, Highways, Investigation, Madurai.

4)The Pay & Accounts Officer, T.P.K. Road, Madurai.

... Respondents Petition filed under Article 226 of the Constitution of India, praying for the issuance of a Writ of Mandamus, directing the respondents 3 and 4 to disburse the pay pension salary arrears of Rs.20,000/- without insisting for 'Non Drawl Certificate' within a time frame fixed by this Hon'ble Court.

For Petitioner : Mr.R.Subramanian For R1 to R3 : Mr.K.P.Krishnadass Government Advocate For R4 : Mr.P.Gunasekaran

ORDER

The prayer in this writ petition is for issuance of a Writ of Mandamus, directing the respondents 3 and 4 to disburse the pay pension salary arrears of Rs.20,000/- without insisting for 'Non Drawl Certificate' within a time frame fixed by this Hon'ble Court.

https://hcservices.ecourts.gov.in/hcservices/

2.The petitioner has written a letter dated 25.09.2015 to the learned Government Advocate that the prayer is complied with by the respondent and that this writ petition has become infructuous. Accordingly, citing the letter dated 25.09.2015 of the petitioner, the 3rd respondent has addressed a letter dated 07.02.2017 to the learned Government Advocate.

3.Placing on record the letters dated 25.09.2015 and 07.02.2017, this Writ Petition is closed.

Sd/- Assistant Registrar(Records) /True copy/ Sub Assistant Registrar To 1)The Government of TamilNadu, Rep. by its Principal Secretary, Highways Department, Fort St.George, Secretariat, Chennai-600 009.

2)The Chief Engineer(H), Designs and Investigation, Block 3, Second floor, SIDCO Electronics Complex, Thiru-vi-ka Industrial Estate, Guindy, Chennai-600 032.

3)The Divisional Engineer, Highways, Investigation, Madurai.

4)The Pay & Accounts Officer, T.P.K. Road, Madurai.

+1cc to M/S.R.Subramanian, Advocate, SR.No:7911 +1cc to Spl. Government Pleader, SR.No:8092 nbi AE/CM MSA/24.02/2017/2P/7C W.P(MD)No.18455 of 2014 13.02.2017 https://hcservices.ecourts.gov.in/hcservices/