P.M.Chellappan, v. The Assistant Director
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 17.07.2017
CORAM
THE HONOURABLE MR.JUSTICE R.MAHADEVAN W.P.(MD)No.17259 of 2015 P.M.Chellappan ... Petitioner Vs.
1.The Assistant Director (Panchayat), Karur District, Karur.
2.The Block Development Officer(Village Panchayats), Karur Panchayat Union, Karur.
3.The Executive Officer, Nanniyur Panchayat, N.Pudur Post, Manmangalam Taluk, Karur District.
4.The President, Nanniyur Panchayat, N.Pudur Post, Manmangalam Taluk, Karur District.
... Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India to issue a Writ of Mandamus directing the 3rd and 4th respondents to implement the order passed by the 1st respondent in Na.Ka.A5/533/2014 dated 18.02.2014 for restoring the water service connection in Connection Nos.2/152 and 2/152-1 of the petitioner's house in N.Pudur, Manmangalam Taluk, Karur District. For Petitioner : Mr.M.Mithun For Respondents : Mr.J.Gunaseelan Muthiah, Government Advocate for R.1 and R.3 Mr.R.Anandharaj, for R.2 Mr.M.Saravana Kumar, for R.4
ORDER
This writ petition has been filed by the petitioner to issue a writ of Mandamus to direct the third and fourth respondents to implement the order passed by the first respondent in Na.Ka.A5/533/2014 dated 18.02.2014 for restoring the water service connection in Connection Nos.2/152 and 2/152-1 of the petitioner's house in N.Pudur, Manmangalam Taluk, Karur District.
2. Heard the learned counsel appearing for the petitioner, the learned Government Advocate appearing for the first and third respondents, the learned counsel appearing for the second respondent and the learned counsel appearing for the fourth respondent. https://hcservices.ecourts.gov.in/hcservices/
3. The grievance of the petitioner is that though the petitioner's representation dated 25.02.2013, to the first respondent seeking water connection to his premises, met with a positive result on 18.04.2013, by the Deputy Block Development Officer, the same has not been carried out by the fourth respondent herein. Thereafter, the petitioner submitted a representation before the District Collector on 27.01.2014, seeking water connection to his premises, upon which, the Block Development Officer has communicated the then President vide proceedings in ef.m5/533/2014 dated 18.02.2014, to provide water connection and report the same. As the same has not been compiled with by the fourth respondent till date, the petitioner filed this writ petition seeking water connection to his premises.
4. Considering the facts and circumstances of the case, the respondents 1 to 3 are directed to consider the request of the petitioner for providing water connection to his premises dated 27.01.2014 and take a decision in line with the proceedings of the Block Development Officer in ef.m.5/533/2014 dated 18.02.2014, within a period of four weeks from the date of receipt of a copy of this order. While considering the request of the petitioner, the other connections given to the nearest buildings shall also be taken into account.
5. The writ petition is disposed of as above. No costs. Sd/- Assistant Registrar(A.E) /True Copy/ Sub Assistant Registrar To 1.The Assistant Director (Panchayat), Karur District, Karur.
2.The Block Development Officer(Village Panchayats), Karur Panchayat Union, Karur.
3.The Executive Officer, Nanniyur Panchayat, N.Pudur Post, Manmangalam Taluk, Karur District.
+1cc to M/s.M.MITHUN Advocate in SR. NO.65854 +1cc to Mr.R.ANANDARAJ Advocate in SR. No.65779 +1cc to Mr.M.SARAVANA KUMAR, Advocate in SR.No.65797 +1cc to THE SPECIAL GOVERNMENT PLEADER in SR. No.66069 GK JS/SKN.RSK/SAR.4/24.7.2017/2P-8C W.P.(MD)No.17259 of 2015 https://hcservices.ecourts.gov.in/hcservices/ 17.07.2017