BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 15.04.2025

CORAM

THE HONOURABLE MR.JUSTICE P.B.BALAJI Sakthivel ... Petitioner Vs.

1.The Tahsildar, Office of the Tahsildar, Srirangam, Trichy District.

2.The Head Surveyor, Office of the Tahsildar, Srirangam, Trichy District.

3.The Inspector of Police, Jeeyapuram Police Station, Trichy District.

4. M.Muthukaruppan ... Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India for issuance of Writ of Mandamus, directing the respondents 1 and 2 to survey the land and fix the boundary stones in connection with Survey No.196/2A, and 206/5 situated at Anthanallur Village, Srirangam Taluk, Trichy District with police protection at the time of survey the land by considering the petitioner's online application No.2024/0123/15/003177 dated 13.09.2024. 1/5

For Petitioner : Mr.A.Subramanian For R1 & R2 : Mr.B.Saravanan Additional Government Pleader For R3 : Mr.S.Prakash Government Advocate

O R D E R

The petitioner seeks issuance of writ of Mandamus to direct the respondents 1 and 2 to conduct survey with the help of the third respondent officials.

2. Heard the learned counsel on either side.

3. Considering the limited relief sought for in this writ petition, this writ petition is taken up for final disposal with the consent of either side.

4. The petitioner has made an application for survey of his lands way back on 13.09.2024. The grievance of the petitioner is that despite passage of several months, no survey has been conducted.

5. The learned Additional Government Pleader for the respondents 1 and 2 submits that the respondents has already acted on the representation of the 2/5

petitioner and survey was attempted by the respondents 1 and 2, however, in view of the obstructions by the fourth respondent, survey could not be conducted. Therefore, he submits that sufficient police protection may be given to enable the respondents 1 and 2 to dispose of the petitioner's application, dated 13.09.2024.

6. In view of the above, the writ petition is disposed of with a direction to the respondents to fix a date for survey and issue advance intimation to the petitioner as well as the fourth respondent and also to the third respondent to enable the third respondent to provide sufficient police protection to the respondents 1 and 2 at the time of survey. The survey shall be conducted in the presence of the parties as well as the police officers. The entire exercise shall be carried out within a period of 8 weeks from the date of receipt of a copy of this order. No costs.

15.04.2025 NCC:yes/no Index:yes/no Internet:yes/no sn 3/5

To:

1.The Tahsildar, Office of the Tahsildar, Srirangam, Trichy District.

2.The Head Surveyor, Office of the Tahsildar, Srirangam, Trichy District.

3.The Inspector of Police, Jeeyapuram Police Station, Trichy District.

4/5

P.B.BALAJI , J.

Sn 15.04.2025 5/5