← Library
Madras High CourtWP(MD)/14483/2018disposed of

P.Muniyan v. The Secretary

2018-07-06Honourable Mr Justice M. Govindaraj3 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 06.07.2018

CORAM:

THE HONOURABLE MR.JUSTICE M.GOVINDARAJ W.P.(MD)No.14483 of 2018 P.Muniyan : Petitioner Vs.

1.The Secretary, Labour and Employment Department, Secretariat, Chennai-9.

2.The Commissioner of Labour, DMS Compound, Thenampettai, Chennai-6.

3.The Secretary, Tamil Nadu Construction Workers Welfare Board, No.8, Valluvarkottam Highways, Nungampakkam, Chennai-34.

4.The Secretary, Tamil Nadu Manual Workers Welfare Board, Chinthamani Commercial Complex, Anna Nagar East, Chennai-102.

5.The Deputy Director, Local Fund Audit Department, Railway Station Road, Dharmapuri-1.

6.The Assistant Commissioner of Labour, Social Security Scheme, District Collectorate, Salem Road, Dharmapuri-1.

: Respondents PRAYER: Writ Petition is filed under Article 226 of the Constitution of India praying for issuance of a Writ of Mandamus, directing the third and fourth respondents to delete the name of this petitioner from the responsibility over the audit Para Nos.23 & 28 of the audit report dated 31.10.2011 for the year 2007-2008 to 2010-2011. For Petitioner :

Mr.G.M.Xavier For Respondents :

Mrs.S.Srimathy, Special Government Pleader

ORDER

The petitioner has come forward with the present Writ Petition seeking for the issuance of a Writ of Mandamus, directing the third and fourth respondents to delete his name from the responsibility over the audit Para Nos.23 & 28 of the audit report dated 31.10.2011 for the year 2007-2008 to 2010-2011.

2. Mrs.Srimathy, learned Special Government Pleader, takes notice on behalf of the respondents.

3. By consent, the Writ Petition is taken up for final disposal at the stage of admission itself.

4. Seeking such relief, the petitioner has sent a representation dated 02.04.2018 to the third respondent and since the same has not been considered so far, the petitioner is before this Court with the present Writ Petition for the reliefs as stated above.

5. Considering the facts and circumstances of the case, without going into the merits of the case, a direction is given to the third respondent to consider and dispose of the representation made by the petitioner dated 02.04.2018 on merits and in accordance with law, within a period of four weeks from the date of receipt of a copy of this order.

6. The Writ Petition is disposed of with the above direction. No costs.

Sd/- Assistant Registrar(CS-III) /True copy/ Sub Assistant Registrar (CS-I) To 1.The Secretary, Labour and Employment Department, Secretariat, Chennai-9.

2.The Commissioner of Labour, DMS Compound, Thenampettai, Chennai-6.

3.The Secretary, Tamil Nadu Construction Workers Welfare Board, No.8, Valluvarkottam Highways, Nungampakkam, Chennai-34.

4.The Secretary, Tamil Nadu Manual Workers Welfare Board, Chinthamani Commercial Complex, Anna Nagar East, Chennai-102.

5.The Deputy Director, Local Fund Audit Department, Railway Station Road, Dharmapuri-1.

6.The Assistant Commissioner of Labour, Social Security Scheme, District Collectorate, Salem Road, Dharmapuri-1.

+1cc to Mr.G.M.Xavier, Advocate, SR.No.71556. +1cc to Special Government Pleader, SR.No.71697. Order made in W.P.(MD)No.14483 of 2018 Dated: 06.07.2018 SML RAM/SV/SAR 1/24.07.2018/3P/9C