Sunrise Knitting Mills (P) Ltd-Weg No.277, v. Pankaj Kumar Bansal
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 23.08.2021
CORAM
THE HONOURABLE MR.JUSTICE SENTHILKUMAR RAMAMOORTHY Sunrise Knitting Mills (P) Ltd., WEG No.277, SF.No.242/3, A(p), 3B(P) of Kuthirakulam Village, Ottapidaram Taluk, Tuticorin District, Represented by its Authorised Signatory R.Palraj ... Petitioner/Petitioner Vs.
1.Shri Pankaj Kumar Bansal Chairman and Managing Director, Tamilnadu Generation and Distribution Corporation Ltd., (TANGEDCO), 10th Floor, 144, Anna Salai, Chennai - 600 002.
2.Mr.M.Ramachandran., B.E., M.C.A., The Chief Engineer, NCES, 2nd Floor, 144, Anna Salai, Chennai - 600 002.
3.Mr.Gnaneswaran, B.E., The Superintending Engineer, Tuticorin Electricity Distribution Circle, Tuticorin.
.. Respondents 1to 3/Contemnors Prayer : Contempt Petition filed under Section 11 of the Contempt of Courts Act, 1971, to punish the respondents for their act of committing Contempt of Court by disobeying the order of this Court dated 26.03.2021, made in W.P.(MD).No.14580 of 2017. PRAYER in W.P.(MD) No.14580 of 2017:Writ Petition filed under Article 226 of the Constitution of India, praying this Court To issue a Writ of Certiorarified Mandamus, calling for the records relating to the issuance of the impugned Proceedings in (CMD) No.266 on 20.05.2017 of the 1st and 2nd respondent and quash the same as not maintainable by law as well as on facts and direct the 1st, 2nd, and 3rd respondents to strictly comply with the provisions of the Constitution of India as enshrined under Article 300 A and confine 1/3
the Respondents within the statutory provisions of Electricity Act 2003 in the matter of allowing the Utility Charges from converting the existing Energy Purchase Agreement to Energy Wheeling Agreement and consequently direct the respondents to allow the captive consumption of the windmill generated units from the petitioner windmill bearing WF HTSC No.277 of Tuticorin EDC for adjustment against consumption at the petitioner's spinning mill at HTSC No.142 at Gobi EDC.
For Petitioner : Mr.R.S.Pandiyaraj For Respondents : Ms.M.Rajeswari for Mr.S.M.S.Johnny Basha Standing Counsel
ORDER
At the last hearing, it was submitted on behalf of the TANGEDCO that the relevant order had been complied with. At the hearing today, learned counsel for the petitioner concurs that the order has been complied with. Consequently, Cont.P.(MD).No.875 of 2021 is closed.
Sd/- Assistant Registrar (CS-II) // True Copy // / /2021 Sub Assistant Registrar(CS) TM Note : In view of the present lock down owing to COVID-19 pandemic, a web copy of the order may be utilized for official purposes, but, ensuring that the copy of the order that is presented is the correct copy, shall be the responsibility of the advocate/litigant concerned.
To:- 1.Shri Pankaj Kumar Bansal Chairman and Managing Director, Tamilnadu Generation and Distribution Corporation Ltd., (TANGEDCO), 10th Floor, 144, Anna Salai, Chennai - 600 002.
2.Mr.M.Ramachandran., B.E., M.C.A., The Chief Engineer, NCES, 2nd Floor, 144, Anna Salai, Chennai - 600 002.
2/3
3.Mr.Gnaneswaran, B.E., The Superintending Engineer, Tuticorin Electricity Distribution Circle, Tuticorin.
23.08.2021 RD(31.08.2021) 3P 4C 3/3