← Library
Madras High CourtWP(MD)/8757/2026disposed of

M/S.Cibi Krishna Textiles Private Limited v. Tamil Nadu Power Distribution Corporation Ltd (Tnpdcl)

2026-04-06Honourable Mr.Justice Hemant Chandangoudar6 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 06.04.2026

CORAM

THE HON'BLE MR.JUSTICE HEMANT CHANDANGOUDAR W.P.(MD)No.8757 of 2026 and W.M.P(MD)No.7085 of 2026 M/s.Cibi Krishna Textiles Private Limited, Rep. by its Authorised Signatory Mr.Thiruvenkatasamy.

.. Petitioner - Vs. -

1. Tamil Nadu Power Distribution Corporation Ltd (TNPDCL), Represented by its Chairman and Managing Director, 10th Floor, Eastern Wing, N.P.K.R.R Maligai, 144, Anna Salai, Chennai.

2. Director / Finance, 144, Anna Salai, Chennai 600 002.

3. The Chief Financial Controller (General), Tamil Nadu Power Distribution Corporation Ltd (TNPDCL) 144, Anna Salai, Chennai 600 002.

4. The Superintending Engineer, Tirunelveli Electricity Distribution Circle, Anna Building, Thiyagaraja Nagar, 1/6

Tirunelveli-627 011.

5. The Superintending Engineer, Theni Electricity Distribution Circle, NRT Nagar Road, Theni 625 531.

.. Respondents Prayer : Writ Petition is filed under Article 226 of the Constitution of India, praying this Court to issue a Writ of Mandamus directing the Respondent and their men, agents not to collect current consumption charges, demand charges, and any arrears from the petitioner for the consumption in HTSC No. 059094760055 connected to the 5th Respondent, till the payment of entire outstanding dues of Rs.2,84,834/- due towards payments for the unutilized units of energy generated by the petitioners WEG bearing HTSC No.079224722750 connected to the 4th Respondent, along with interest at 1 percent per month, until the said amount is either paid or adjusted in full by the Respondents. For Petitioner : Mr.Rahul Balaji For Respondents : Mr.S.Deenadhayalan Standing Counsel

ORDER

Mr.S.Deenadhayalan, learned Standing Counsel accepts notice for the respondents.

2/6

2. The petitioner is before this Court seeking a direction to the respondents forbearing them from collecting current consumption charges, demand charges, and any arrears from the petitioner for the consumption in HTSC No. 059094760055. Petitioner claims to a captive power generator and supplied energy to the TANGEDCO and a certain amount is due to the TANGEDCO and without adjusting the said amount, the respondents are demanding payment of monthly consumption charges for the stock.

3. Mr.S.Deenadhayalan, learned counsel appearing for TANGEDCO submitted that if any amount is due to the petitioner, the same shall be adjusted towards the consumption charges.

4. The said submission is taken on record.

5. This Writ Petition is disposed of directing the first respondent to adjust the amount, if any, due to the petitioner from the consumption charges to be paid by the petitioner in relation to the said service connection. If the petitioner is found entitled for the amount on account of supply of energy to the respondent, the same shall be deducted from the monthly consumption charges 3/6

for the month of April, 2026. There shall be no orders as to costs. Consequently, connected miscellaneous petition is closed. 06.04.2026 Index :Yes/No Internet :Yes/No NCC :Yes/No PJL To

1. Tamil Nadu Power Distribution Corporation Ltd (TNPDCL), Chairman and Managing Director, 10th Floor, Eastern Wing, N.P.K.R.R Maligai, 144, Anna Salai, Chennai.

2. Director / Finance, 144, Anna Salai, Chennai 600 002.

3. The Chief Financial Controller (General), Tamil Nadu Power Distribution Corporation Ltd (TNPDCL) 144, Anna Salai, Chennai 600 002.

4. The Superintending Engineer, Tirunelveli Electricity Distribution Circle, Anna Building, Thiyagaraja Nagar, Tirunelveli-627 011.

4/6

5. The Superintending Engineer, Theni Electricity Distribution Circle, NRT Nagar Road, Theni 625 531.

5/6

HEMANT CHANDANGOUDAR, J.

PJL W.P.(MD)No.8757 of 2026 06.04.2026 6/6