← Library
Madras High CourtWP(MD)/8949/2015disposed of

Mathialagan, v. The District Collector

2015-06-04Honourable Mr Justice R. Mahadevan2 pages

BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED :04.06.2015

CORAM

THE HONOURABLE MR.JUSTICE.R.MAHADEVAN W.P(MD).No.8949 of 2015 1.Mathialagan 2.Kalyani 3.M.Tamilselvi 4.Sumathi ... Petitioners Vs 1.The District Collector, Pudukkotai.

2.The Tashildar, Kulathur, Pudukkotai District.

3.The Assistant Engineer (Operation and Maintenance), TANGEDCO, Mathur Post, Kulathur Taluk, Pudukkotai District.

...

Respondents This Writ Petition has been filed under Article 226 of the Constitution of India for the issuance of Writ of Mandamus to direct the third respondent to give electricity service connection to the petitioner's house comprised in S.F.No.206/2 of Mathur Village, Kulathur Taluk, Pudukkotai District. For petitioner : Mr.P.Ganapathi Subramanian For R.1&2 : Ms.S.Bharathi Govt.Advocate For R.3 : Mr.S.M.S.Johny Basha

ORDER

This Writ Petition has been filed praying for a Writ of Mandamus to direct the third respondent herein to give electricity connection for the house of the petitioner.

https://hcservices.ecourts.gov.in/hcservices/

2. By consent, this Writ Petition is taken up for final disposal at the admission stage.

3. Mrs.S.Bharathi, learned Government Advocate takes notice for the respondents 1 and 2 and Mr.S.M.S.Johny Basha, learned Standing Counsel takes notice for the third respondent.

4. When the matters are taken-up for hearing, both the parties mutually agreed upon to pass order on the basis of the earlier order of this Court dated 15.04.2013 in W.P.(MD).No.3769 of 2013, wherein, in paragraph No.6, it is held as follows:- "6.The petitioners are directed to approach the Tahsildar, Kulathur to execute an undertaking affidavit to the effect that they will vacate the property in the event of Government requires the lands, for the purpose of obtaining 'No Objection Certificate' should be given by the Tahsildar, Kulathur within two weeks from the date of such undertaking. Similarly, in the event of producing 'No Objection Certificate' by the petitioners before the second respondent, the application for electricity connection should be considered and dispose of within a period of two weeks from the date of receipt application."

Following the said order dated 15.04.2013 in W.P.(MD).No.3769 of 2013, this Writ Petition is also disposed of. No costs. Sd/- Assistant Registrar(T&P) /True Copy/ Sub-Assistant Registrar To 1.The District Collector, Pudukkotai.

2.The Tashildar, Kulathur, Pudukkotai District.

3.The Assistant Engineer (Operation and Maintenance), TANGEDCO, Mathur Post, Kulathur Taluk, Pudukkotai District.

+One cc to Mr.P.Ganapathi Subramanian, Advocate, SR.No.27831 +One cc to The Special Government Pleader, SR.no.28024 ssm RL/6 c- 19/6/2015 W.P(MD).No.8949 of 2015 04.06.2015 https://hcservices.ecourts.gov.in/hcservices/