1 W.P.(MD)NO.11776 OF 2024 BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED : 06.06.2024

CORAM

THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN W.P.(MD)No.11776 of 2024 M.Saravanan ... Petitioner Vs.

1. The Superintending Engineer, Transmission Line Circle, Tamil Nadu Transmission Corporation Ltd.,(TANTRANSCO), Mannarpuram, Tiruchirappalli.

2. The Executive Engineer, Tamil Nadu General and Distribution Corporation Ltd., (TANGEDCO), TNEB Complex, No.3, Kovai Road, Karur - 639 002.

3. The Commissioner, Karur Municipal Corporation, Karur.

4. The Superintending Engineer (Operation), TNEB Complex, Near Collector Office, Trichy.

(R-4 is suo motu impleaded vide order dated 06.06.2024) ... Respondents Prayer: Writ petition filed under Article 226 of the Constitution of India, to issue a Writ of Mandamus, directing the respondents 1 and 2 to grant 'No Objection Certificate' for the construction of house in plot Nos.13 and 14 situated in S.F.No.44/1J in Inam Karur Village, Karur Taluk, Karur District, subject to compliance 1/4

2 W.P.(MD)NO.11776 OF 2024 with the prescribed clearance guidelines and further directing the third respondent to process and grant the building plan approval without any further delay by considering the representation dated 20.05.2024 within a stipulated time that may be fixed by this Court. For Petitioner : Mr.A.N.Ramanathan For R-1, R-2 & R-4: Mr.S.Deenadhayalan, Standing counsel.

For R-3 : Mr.K.Balasubramanian, Special Government Pleader.

* * *

O R D E R

Heard both sides.

2. The petitioner owns the petition mentioned plot. It is located under a running high tension line. For putting up construction, NOC is required.

3. The petitioner is permitted to submit a fresh application before the fourth respondent. The fourth respondent will conduct spot inspection. The fourth respondent shall suggest appropriate ways and means and also stipulate relevant conditions regarding construction. Final order on merits and in accordance with law will be passed by the 2/4

3 W.P.(MD)NO.11776 OF 2024 fourth respondent within a period of three weeks from the date of submission of application by the petitioner herein. This writ petition stands disposed of accordingly. No costs.

06.06.2024 NCC : Yes / No Index : Yes / No Internet : Yes/ No PMU To:

The Commissioner, Karur Municipal Corporation, Karur.

3/4

4 W.P.(MD)NO.11776 OF 2024 G.R.SWAMINATHAN,J.

PMU W.P.(MD)No.11776 of 2024 06.06.2024 4/4