P.Satheeshkumar v. The Chief Engineer(Personal)
BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 14.07.2017
CORAM:
THE HONOURABLE MR.JUSTICE R.MAHADEVAN W.P(MD)No.11322 of 2017 and W.M.P(MD)No.8696 of 2017 P.Satheeshkumar ... Petitioner Vs.
1. The Chief Engineer (Personal) Tamilnadu Generation and Distribution Corporation Ltd., Administrative Branch, 144, Anna Salai, Chennai.
2. The Superintending Engineer, Tamilnadu Generation and Distribution Corporation Ltd., Karur Electricity Distribution Circle, Karur.
3. The Superintending Engineer, Tamilnadu Generation and Distribution Corporation Ltd., Thanjavur Electricity Distribution Circle, Thanjavur.
... Respondents Prayer: Petition filed under Article 226 of the Constitution of India, to issue a Writ of Mandamus to direct the the third respondent to implement the Transfer order issued by the first respondent dated 30.05.2017 and consequently direct second respondent to relive the petitioner from Karur circle so as to enabling him to join in Thanjavur Circle.
For Petitioner ... Mr.M.Siddharthan For R.1 toR.3 ... Mr.E.P.Venkateshwar, For S.M.S.Johny Basha
ORDER
This writ petition has been filed, seeking to direct the third respondent to implement the Transfer order issued by the first respondent dated 30.05.2017 and consequently direct second respondent to relive the petitioner from Karur circle so as to enabling him to join in Thanjavur Circle.
https://hcservices.ecourts.gov.in/hcservices/
2.When the matter is taken up for hearing, the learned counsel for the petitioner has circulated a letter to the registry for withdrawal of the case, based on the instructions given by the petitioner.
3. In view of the above, this writ petition is dismissed as withdrawn. No costs. Consequently, connected Miscellaneous petition is closed.
Sd/- Assistant Registrar (CO) /True Copy/ Sub Assistant Registrar To:
1. The Chief Engineer (Personal) Tamilnadu Generation and Distribution Corporation Ltd., Administrative Branch, 144, Anna Salai, Chennai.
2. The Superintending Engineer, Tamilnadu Generation and Distribution Corporation Ltd., Karur Electricity Distribution Circle, Karur.
3. The Superintending Engineer, Tamilnadu Generation and Distribution Corporation Ltd., Thanjavur Electricity Distribution Circle, Thanjavur.
+ 1 CC TO Mr.M.SIDHARTHAN, ADVOCATE IN SR No. 65738 RM/AR TE/JC/SAR-III : 27/07/2017 : 2P/5C W.P(MD)No.11322 of 2017 and W.M.P(MD)No.8696 of 2017 14.07.2017 https://hcservices.ecourts.gov.in/hcservices/