BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT DATED: 07.07.2017

CORAM:

THE HONOURABLE MR.JUSTICE K.K.SASIDHARAN and THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN W.P.(MD)No.11641 of 2017 and W.M.P.(MD).No.8978 of 2017 R.Chellamuthu .. Petitioner Vs.

1. The District Collector, Dindigul District, Dindigul.

2. The Divisional Engineer, Office of the Divisional Engineer [North], Southern Railways, Arasaradi, Madurai.

.. Respondents PRAYER: Petition filed under Article 226 of the Constitution of India to issue a Writ of Mandamus, directing the respondents to consider the representation of the petitioner dated 17.12.2016 and 27.03.2017 and erect manned level crossing at Gate No.60, Ponnapuram 17th Ward, Ayakudi Town Panchayat, Palani Taluk, Dindigul District within a time frame that may be stipulated by this Court.

For petitioner : Mr.R.R.Kannan For respondent No.1 : Mr.M.Govindan Special Government Pleader For Respondent No.2 : Mr.S.Manohar Standing Counsel

O R D E R

*********** [Order of the Court was made by K.K.SASIDHARAN, J.] The petitioner submitted representations to the second respondent to erect manned level crossing at Gate No.60, Ponnapuram 17th Ward, Ayakudi Town Panchayat, Palani Taluk, Dindigul District. The representations dated 17.12.2016 and 27.03.2017 are stated to be pending on the file of the second respondent.

2. We have heard the learned counsel appearing for the petitioner, the learned Special Government Pleader appearing for the first respondent and the learned Standing Counsel appearing for the second respondent.

https://hcservices.ecourts.gov.in/hcservices/

3. We direct the second respondent to consider the representations dated 17.12.2016 and 27.03.2017 on merits and as per law and taking note of the grievance raised by the petitioner and the other villagers. Such exercise shall be completed within a period of six weeks from the date of receipt of a copy of this order.

4. The Writ Petition is disposed of with the above direction. No costs. Consequently, connected Miscellaneous Petition is closed.

Sd/- Assistant Registrar(CS-II) /True Copy/ Sub Assistant Registrar To:

1. The District Collector, Dindigul District, Dindigul.

2. The Divisional Engineer, Office of the Divisional Engineer [North], Southern Railways, Arasaradi, Madurai.

+1cc to Mr.R.R.Kannan, Advocate SR.No.63903 NB VB/SV/SAR1/17.07.2017/2P/4C ORDER MADE IN W.P.(MD)No.11641 of 2017 07.07.2017 https://hcservices.ecourts.gov.in/hcservices/